Boiler MACT rule now in effect

A Federal appeals court has ruled that the compliance date for the Boiler MACT rule for facilities is March 21, 2012.

02/03/2012


The District of Columbia Circuit Court of Appeals has reinstated the original compliance date for the Boiler MACT (maximum achievable control technology, also known as BMACT or Major Source Rule) that the EPA published in the Federal Register in March 2011. In a ruling on Jan. 9, 2012, District Court Judge Paul Friedman said that a delay of the rules was “arbitrary and capricious” and negated the delay. As a result, owners and operators of certain boilers and process heaters are required to meet work practice standards outlined in the rule by March 21, 2012 and install MACT equipment by March 2014.

Major source facilities are the ones affected by the newly reinstated Boiler MACT. A major source facility is one that emits 10 or more tons per year of any single air toxic or 25 tons or more per year of any combination of air toxics. A comprehensive list of the regulated air toxics can be found on the EPA website. Very large industrial facilities, such as refineries, chemical and large manufacturing plants, and large institutional facilities such as universities typically are classifed as major source facilities.

If a facility is not a major source, it is classified as an area source and is required to meet a different set of regulations that are in effect. For more information about the Area Source Rule, visit www.cleaverbrooks.com/epa.

Requirements for both major source and area source facilities vary depending upon: the type of fuel combusted, boiler commissioning date, and boiler size. For the Major Source Rule, EPA has identified 15 different subcategories of boilers and process heaters based on the design of the various types of units. The final rule includes specific requirements for each subcategory. Necessary actions range from conducting regular tune-ups to meeting numeric emissions limits. Facilities also must maintain records and file periodic reports to demonstrate compliance.

Below is a summary of the requirements of the Boiler MACT for major source facilities. For the complete rule that is published in the Federal Register, visit http://www.gpo.gov/fdsys/pkg/FR-2011-03-21/pdf/2011-4494.pdf 

- For all new and existing gas- and refinery gas-fired units, the operator must perform an annual tune-up for each unit. Units combusting other gases can qualify for work practice standards by demonstrating that they burn “clean fuel,” with contaminant levels similar to natural gas.

- For all new and existing units with a heat input capacity less than 10 MMBtu/hr, the operator is required to perform a tune-up for each unit once every two years.

- For all new and existing “limited use” boilers (defined as those operated less than 10 percent of the year as emergency and back-up boilers to supplement process power needs), the operator is required to perform a tune-up for each unit once every two years.

- The final rule establishes numeric emission limits for all other existing and new boilers and process heaters located at major sources. The final rule establishes emissions limits for:

  • Mercury
  • Dioxin
  • Particulate matter (PM) as a surrogate for non-mercury metals
  • Hydrogen chloride (HCI) as a surrogate for acid gases 
  • Carbon monoxide (C) as a surrogate for non-dioxin organic air toxics.

- The largest major source boilers are required to continuously monitor their particle emissions. All units larger than 10 MMBtu/hr must monitor oxygen as a measure of good combustion.

- Existing major source facilities are required to conduct a one-time energy assessment to identify cost-effective energy conservation measures.

While the Area Source Rule has been in effect since being published in March 2011, the Major Source Rule has not. In May 2011, EPA issued a notice of delay and asked for a stay of the rules to give the agency more time to evaluate feedback from the industry.

In July 2011, the Sierra Club petitioned the appellate court for review of the EPA’s delay notice, contending that the original rules will help reduce illnesses such as lung cancer and asthma. EPA issued a revised proposal in December 2011 that agency officials said is less costly for affected boiler owners than the original proposal, but still meets the necessary requirements laid out in the 1990 Clean Air Act amendments. However, Judge Friedman’s ruling reinstates compliance deadlines set in the earlier March 2011 rule.



Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
2017 MEP Giants; Mergers and acquisitions report; ASHRAE 62.1; LEED v4 updates and tips; Understanding overcurrent protection
Integrating electrical and HVAC for energy efficiency; Mixed-use buildings; ASHRAE 90.4; Wireless fire alarms assessment and challenges
Integrated building networks, NFPA 99, recover waste heat, chilled water systems, Internet of Things, BAS controls
Transformers; Electrical system design; Selecting and sizing transformers; Grounded and ungrounded system design, Paralleling generator systems
Commissioning electrical systems; Designing emergency and standby generator systems; VFDs in high-performance buildings
Tying a microgrid to the smart grid; Paralleling generator systems; Previewing NEC 2017 changes
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Fire & Life Safety Engineer; Technip USA Inc.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me