By Rick Glenn, P.E., Project Manager, Schirmer Engineering Corporation, Deerfield, Ill. -- Consulting-Specifying Engineer, 5/1/2005

Editor's note: Many eyes are on Chicago now that it has adopted one of the nation's first mandatory sprinkler ordinances for non-residential high-rises. Following is a breakdown of the city's initial requirements for other municipalities considering Chicago as a would-be model.

On Dec. 15, 2004, the city of Chicago adopted a high-rise fire-safety ordinance estimated to affect approximately 1,300 buildings. Among its provisions is a requirement for all high-rise buildings to be retrofitted with automatic fire-sprinkler systems. Open-air parking facilities, open-air portions of stadiums, non-transient residential buildings and designated landmark or historic buildings are exempt. That being said, all non-transient residential buildings, such as condominiums and apartment buildings, as well as historic buildings, have all been ordered to undergo a life-safety evaluation (LSE) in lieu of sprinklers.

The first major milestone came this past month, when all high-rise owners/managers were required to submit a life-safety data sheet. This one-page form requests general information about the building and its existing fire-protection system. It is anticipated that completed forms will be used to create a database for all high-rises so that the city can track compliance.

To assist building managers in establishing accurate budgets and realistic schedules for sprinkler retrofits, detailed compliance plans should address the following:

  • Adequacy of existing water supply to serve the new sprinkler systems.
  • Proposed locations for new equipment, such as sprinkler-system risers and floor control-valve stations.
  • Sprinkler-system design criteria/materials.
  • Impact of asbestos-containing materials (ACM)on the system installations.
  • Project phasing/schedules.
  • Budgetary construction cost estimates.
  • Options and alternatives.

In addressing sprinkler-system design criteria and materials, it is important that plan preparers be aware that the ordinance permits new sprinkler systems to be designed in accordance with the 2002 edition of NFPA 13, which permits lower design densities for certain occupancies. Unlike previous editions, it also allows existing water supplies to serve both standpipe and sprinkler systems, listed plastic piping and the use of extended-coverage sprinklers. Allowing the sprinkler systems to be designed and installed in accordance with the 2002 edition of NFPA 13, instead of current requirements, will permit systems to be installed more cost-effectively without compromising safety.

The preparer of the compliance plan should also obtain information on the presence of any ACM in the building. The types and locations of ACM can have a significant impact on the cost of the system installation.

As with any construction project, there are always options and alternatives to consider. The compliance-plan preparer should review all available options and alternatives with the building owner/manager for their input. Doing so will ensure that the owner/manager is involved in the design process and should help in developing more accurate project schedules and construction cost estimates.

 

Compliance Plan Pluses

  • Building owner involved earlier in design process
  • Major design issues addressed before construction documents are prepared
  • Sprinkler-system installations coordinated with planned renovations
  • Project schedules and construction cost estimates are more accurate
Email
Print
Reprint
Learn RSS

Talkback

We would love your feedback!

Post a comment

» VIEW ALL TALKBACK THREADS

Related Content

Related Content

 

By This Author

There are no other articles written by this author.



SPONSORED LINKS

 
Advertisement
Sponsored Links

More Content

  • Blogs
  • Podcast

Blogs

  • Michael Ivanovich
    Give and Take

    June 19, 2008
    After the flood: mold. Learning from Katrina.
    As Iowa’s flood waters recede and recovery ramps up, the race begins to minimize problems with...
    More
  • Michael Ivanovich
    Give and Take

    June 12, 2008
    Useful Green Building Data and Reports
    There have been some good reports released this year on green buildings. Some folks haven't year hea...
    More
  • » VIEW ALL BLOGS RSS

Podcast

Senior Editor Amara Rozgus (pictured) speaks with John Suzukida, PE, president of Lanex Consulting LLC, Shoreview, Minn. This conversation is about the role of electricity in the future and zoned heating and cooling.
Cooling People, Not Buildings with John Suzukida, PE
Senior Editor Amara Rozgus (pictured) speaks with John Suzukida, PE, president of Lanex Consulting LLC, Shoreview, Minn. This conversation is about the role of electricity in the future and zoned heating and cooling.
Listen Now | Download MP3 | Subscribe
» VIEW ALL PODCASTS Subscribe Now to HVAC & Building Automation and never miss an episode
Advertisements





NEWSLETTERS
Plug in and get the latest CSE news, trends and industry updates delivered directly to your inbox!

Green Scene
CSE Codes & Standards
CSE NewsWatch
CSE Fire and Life Safety Solutions
CSE Business of Engineering Management Report
CSE Electrical Solutions
CSE HVAC Solutions
Pure Power
CSE Product Showcase
©2008 Reed Business Information, a division of Reed Elsevier Inc. All rights reserved.
Use of this Web site is subject to its Terms of Use | Privacy Policy
Please visit these other Reed Business sites