Project: TriMet Powell Garage Bus Administration, Operations & Maintenance Facility
A project requirement was for the existing Powell facility to remain operational during construction.
Engineering firm: Stantec
2024 MEP Giants rank: 11
Project: TriMet Powell Garage Bus Administration, Operations & Maintenance Facility
Location: Portland, OR, United States
Building type: Utilities/public works/transportation
Project type: New construction
Engineering services: Electrical, power; energy, sustainability; lighting
Project timeline: July 2018 to December 2023
Challenges
A project requirement was for the existing Powell facility to remain operational during construction. TriMet did not have the ability to completely close the base during construction because each of their depot bases was already overloaded.
Solutions
Stantec developed a phasing strategy that would allow the CMGC partner and TriMet to plan accordingly, while having the ability to adjust as necessary.
-
Phase 1: Construction fuel and wash
-
Phase 2: Construct the initial phase of the AOM building (approximately 1/2 of the facility), move the reduced count bus fleet to the north end of the site
-
Phases 3-5: Construct bus yard, BEB infrastructure, Powell Boulevard, and SE 99th Street improvements
-
Phases 6-7: Construct second half of the AOM building, employee parking lot, permanent security fencing and gates.