January 3 Southland Industries update: Roughing-in systems continues; drywall installations; West Clinic ceilings started
Roughing-in systems continues; drywall installations; West Clinic ceilings started
As of Jan. 3, 2014:
- Currently roughing-in systems on Levels 2 through 6 in the hospital. Basement, Levels 1, 2, 3, and 4 drywall walls are underway.
- The North Clinic has drywall walls being put up in all areas. The West Clinic’s ceilings have started. The South Clinic rough-in is underway on Levels 1-3.
- All three parking garages are underway.