March 4 Southland Industries update: Roughing in systems, ceilings and diffusers complete, parking garages underway, beginning to prepare to start chilled water plant
Roughing in systems on levels 2, 4, 5, and 6; ceilings and diffusers are complete or near completion; all 3 parking garages are underway; preparation to started the chilled water plant is underway.
February 12 Southland Industries update: Hospital Levels 2, 4, 5, and 6 being roughed-in; South Clinic Level 1 drywall installation; Parking garages underway
Hospital Levels 2, 4, 5, and 6 being roughed-in; South Clinic Level 1 drywall installation; Parking garages underway
January 3 Southland Industries update: Roughing-in systems continues; drywall installations; West Clinic ceilings started
Roughing-in systems continues; drywall installations; West Clinic ceilings started
December 2 Southland Industries update: Roughing in systems on Levels 2-6; Drywall in North, West clinics; Parking garages underway
Roughing in systems on Levels 2-6; Drywall in North, West clinics; Parking garages underway
November 1 Southland Industries update: Roughing-in Levels 2 and 5; temporary air conditioning; parking garages
Roughing-in systems on Levels 2 and 5; North and West Clinics being prepared for temporary air conditioning; CUP stream plant being finalized; three parking garages underway.
September 30 Southland Industries update: Mechanical room equipment, cooling towers passivated, chilled water system insulation
Roughing in systems on Levels 1 to 4, connecting equipment in main mechanical rooms, North and West clinics near completion, cooling towers being passivated, chilled water system getting insulation.
September 3 Southland Industries update: Rough testing began, major equipment placed, condenser water system flushed
Rough testing has begun in hospital basement, Level 1; all major equipment has been set in place; the condenser water system is being flushed and passivated in the CUP.
July 29 Southland Industries update: Level 3 air handling units set, condenser water system testing
Hospital Level 3 air handling units have been set; Condenser water system in the CUP is being tested; Rough in testing begun in the west clinic.
July 8 Southland Industries update: rough in, testing of plumbing systems completed
Continuing rough in on interstitial levels of North and West clinics; completed rough in and testing of plumbing systems; CUP steam boilers arrived, being installed.
June 3 Southland Industries update: mechanical room open
Currently roughing in on interstitial levels of the North and West clinics; the Level 3 mechanical room has opened up; trade installations have begun.