December 2 Southland Industries update: Roughing in systems on Levels 2-6; Drywall in North, West clinics; Parking garages underway
Roughing in systems on Levels 2-6; Drywall in North, West clinics; Parking garages underway
As of Dec. 2, 2013:
- Currently roughing in systems on Levels 2 through 6 in the hospital. Basement and Level 1 drywalls underway.
- The North and West Clinics have drywall walls being put up in all areas. The South Clinic rough-in is underway in Levels 1 through 3.
- All three parking garages are underway.