Roof installation is in progress over the school gymnasium.
June 2017 Update:
General work
- Building CMU walls are being erected throughout.
- Steel erection in progress.
- Brick veneer installation is about to begin.
- All underground site utilities are being installed along with the site grading work.
- Second floor slab has been poured in half the school.
- Roof installation in progress over gymnasium portion of school.
Mechanical/electrical/plumbing
- First-floor plumbing piping installation is in progress.
- First-floor electrical conduit and feeder installation in progress.
- First-floor mechanical ductwork and hydronic piping installation in progress.