South Clinic TAB is completed. Functional performance testing on the boiler system, water softener, and domestic water heat exchangers is underway.

March 2015 update:
- South Clinic has been turned over to the client for equipment delivery.
- South Clinic functional performance tests are completed.
- Chlorination of the domestic water system in the clinics is completed.
- Hospital TAB for the basement and level 1 is completed.
- Hospital basement has been turned over to the client for equipment delivery.
- Hospital level 1 is projected to be turned over to U.S. Army Corps of Engineers mid-March.
- Steam system load test is completed along with functional performance testing.