South Clinic TAB is completed. Functional performance testing on the boiler system, water softener, and domestic water heat exchangers is underway.

January-February 2015 update:
- South Clinic test and balance (TAB) is completed.
- South Clinic punchlist activities are nearing completion.
- Hospital TAB is underway.
- Hospital Basement and level 1 finish are nearing completion.
- Hospital Basement projected to be turned over to U.S. Army Corps of Engineers mid-February.
- MRI equipment has been delivered, utilities connected and commissioned.
- Functional performance testing on the boiler system, water softener, and domestic water heat exchangers is underway.