May 1 Southland Industries update: CUP nearly complete
The central utility plant is currently 80% complete; the project team recently hung four Armstrong vertical inline 1,900 gpm chilled water pumps; the boiler flue gas economizers have been hung.
As of May 1, 2013:
- The central utility plant (CUP) is currently 80% complete (see Figure 1 in the slideshow below)
- The project team recently hung four Armstrong vertical inline 1,900 gallons per minute (gpm) chilled water pumps (see Figure 2).
- The boiler flue gas economizers have been hung and are awaiting boiler flue and boilers (see Figure 3).
Additional comments:
- We will be circulating water in the chiller plant in the coming months and are awaiting delivery of the boilers in July.
- Below are some interesting stats about the project that might be of interest. For your reference, much of the sustainable-conscious design used in the CUP helps attribute to the energy and water savings projected below.
- 786,965 cfm AHU supply volume
- 37,063,905 kWh annual electricity use, 11.7% savings over ASHRAE baseline
- 39,697 therms annual natural gas use, 92.8 % savings over ASHRAE baseline
- Overall 34.3% energy savings over ASHRAE baseline
- 8,112,515 gal of water used per year, 40% savings over baseline
- 46,864-MBH steam boiler plant
- 5,422-ton chiller plant
- 393,227 LF (74.5 miles) of pipe
- 1,302,485 lbs (651.2 tons) of sheetmetal
Gary Lovewell is a senior project manager at Southland Industries.
Do you have experience and expertise with the topics mentioned in this content? You should consider contributing to our WTWH Media editorial team and getting the recognition you and your company deserve. Click here to start this process.