Electrical, power; vehicle charging station; and existing building retrofit
Engineering firm: CDM Smith
2018 MEP Giants rank: 63
Project: Indianapolis Airport Electric Vehicle Charging
Location: Indianapolis, Indiana, United States
Building type: Electric vehicle charging station
Project type: Existing building retrofit
Engineering services: Electrical, power
Project timeline: June 2016 to December 2017
MEP/FP budget: $123,340
Challenges
The retrofit of the electric system to accommodate the electric vehicle charging infrastructure was a challenge for this project.
Solutions
CDM Smith’ssolution was to develop a detailed design using a preselected charging infrastructure vendor and to perform a detailed investigation of the existing infrastructure.