High standards for labs, research buildings: HVAC systems

Laboratory and research facilities are high-performance buildings, often with complex systems and exacting standards for engineers to meet. HVAC systems and indoor air quality are key issues.

05/22/2014


Bryan Laginess, PE, LEED AP, Senior associate, Peter Basso Associates, Troy, Mich. Jeremy Lebowitz, PE, Vertical market leader, Rolf Jensen & Associates Inc., Framingham, Mass.Brian Rener, PE, LEED AP, Associate, SmithGroupJJR, ChicagoJoshua Yacknowitz, PE, LEED AP, Associate principal, Arup, New York City

  • Bryan Laginess, PE, LEED AP, Senior associate, Peter Basso Associates, Troy, Mich.
  • Jeremy Lebowitz, PE, Vertical market leader, Rolf Jensen & Associates Inc., Framingham, Mass.
  • Brian Rener, PE, LEED AP, Associate, SmithGroupJJR, Chicago
  • Joshua Yacknowitz, PE, LEED AP, Associate principal, Arup, New York City

Colleges and universities frequently are home to laboratory and research facilities. Renovations such as the Michigan Memorial Phoenix Laboratory at the University of Michigan can help such institutions keep up with the latest advancements. Courtesy: Peter Basso Associates Inc., Camille Sylvain Thompson photographerCSE: What unique HVAC requirements do laboratory/research facility structures have that you wouldn’t encounter on other structures?

Laginess: Laboratories usually require a high air change rate, and usually require 100% outside air. From an energy standpoint, it is a very costly operation. Although not always required, energy recovery systems are commonly used to reduce the operating cost.

Yacknowitz: Once-through air requirements in many lab types; control zone fire separation and need to segregate exhaust risers in shafts; specialized exhaust systems such as radioisotope and perchloric acid, which require dedicated exhaust systems and special controls; fast-acting terminal air valves for control of airflows in labs; and minimum air change rates in lab spaces, to name a few.

CSE: What changes in fans, variable frequency drives, and other related equipment have you experienced?

Yacknowitz: Variable frequency drives (VFDs) are quite common nowadays because the cost of these controllers is quite low compared to years ago. In labs, however, depending on the science, there may be a need to provide 12- or 18-pulse VFDs in order to control harmonic distortion in the building power grid. These VFDs are more expensive and often require significantly more space to install. We have also seen more dc motors for small systems such as clean room fan filter units, as these motors are infinitely adjustable in terms of speed and run at high efficiency.

CSE: In your experience, have alternative HVAC systems become more relevant?

Laginess: We are seeing an increased use of chilled beams in laboratory projects. The design approach is very different from the standard air systems. This system can reduce energy costs and require less space for installation. I think that as we see energy costs continue to rise, alternative methods will become standard.

Yacknowitz: Chilled beams are becoming more acceptable, particularly in nonchemistry labs where recirculation of air within the lab is not as much of a health or safety risk.

CSE: Do you find it more challenging to retrofit HVAC systems on older buildings than installing on new?

Laginess: It is more challenging to retrofit HVAC systems on older buildings than to install them on a new building. The design team has much more control over the systems used and how they fit into the facility when they can start with a clean slate.

Yacknowitz: Generally, it is easier in new buildings since the current code requirements for control zoning, shaft segregation, and other factors can be planned into the structural and floor plan arrangement of the building. Older buildings are often built to older codes, which makes it difficult to meet current control zone, shaft space, and floor-to-floor height requirements that result from current codes and standards. However, there is generally a huge opportunity to dramatically increase energy efficiency in older labs.



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Water use efficiency: Diminishing water quality, escalating costs; Lowering building energy use; Power for fire pumps
Building envelope and integration; Manufacturing industrial Q&A; NFPA 99; Testing fire systems
Labs and research facilities: Q&A with the experts; Water heating systems; Smart building integration; 40 Under 40 winners
Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.