BRAC 133 at Mark CenterProject name: BRAC 133 Office Towers

Location: Arlington, Va.

Firm name: Sebesta Blomberg

Project type, building type: Existing building retrofit, office

Project duration: 2.7 years

Project completion date: Sept. 15, 2011

Engineering challenges

This fast-track design-build project required an intense level of rigor from Sebesta Blomberg. High-end security systems, state-of-the-art HVAC strategies, and complex building automation systems were thoroughly tested while accommodating a compressed schedule. More than 1,500 functional performance tests were developed, conducted, and tracked to completion to ensure that building systems operate effectively. Aggressive scrutiny was applied to key components, such as central plant heating/cooling systems, data centers, building control centers, and emergency electrical systems.

Solutions

Sebesta Blomberg drew on its national corporate presence and assembled an experienced team to accommodate the demanding schedule and extraordinary scope of work. Equipment and systems were tested as they became available. Unparalleled flexibility and clear communication lines were required and established with project stakeholders. Construction completion and full complex operation were achieved one month ahead of schedule.



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Emergency lighting; NFPA 3 and 4; Integrated building systems; Smart lighting, HVAC design
Designing for energy efficiency; Understanding and applying NFPA 101 for mission critical facilities; Integrating commissioning and testing for fire alarm systems; Optimizing unitary pumping solutions
Economics of HVAC systems; NFPA 110-2016; Designing and choosing modular data centers
Tying a microgrid to the smart grid; Paralleling generator systems; Previewing NEC 2017 changes
Driving motor efficiency; Preventing Arc Flash in mission critical facilities; Integrating alternative power and existing electrical systems
Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Fire & Life Safety Engineer; Technip USA Inc.
click me