Using IPD and Lean in building design

Consider integrated project delivery (IPD) and Lean design to provide a more streamlined engineering process and less waste.


Learning objectives

  • Understand the key aspects of integrated project delivery (IPD) as it relates to building construction.
  • Learn how incorporating Lean can eliminate waste in the engineering process.
  • Know how to combine IPD and Lean processes to streamline building engineering.

When we think of the best way to deliver a product, some of us might think of the UPS slogan, "We Love Logistics." But how often do you think about the logistics involved with delivering building projects more effectively? 

Many of us think about the manufacturing industry as a way to streamline production. The Toyota Production System focuses on the elimination of waste. It is not important how many cars are produced,but rather that the best car is produced.

Another place to look is in the kitchen. Chefs learn mise-en-place during training at places like the Culinary Institute of America. There, they learn to gather and arrange the ingredients to help them focus on the meal preparation. In some cases, chefs will spend 6 hours prepping for 3 hours of meal production.

When you look at the engineering industry, it seems the focus has turned away from these practices and is solely on the speed of production, not the quality of the work. Imagine if the schematic phase of the project was twice as long as the production phase. A trend is building to reorient our processes and use other industries as a guide to produce better building design and construction projects with fewer errors and less waste-and that deliver better value to the owner. Lean design and construction is a process that focuses on these areas to deliver a better product.

Lean: Is this IPD?

Often, we use the concepts of integrated project delivery (IPD) and Lean interchangeably. While they are concepts that partner well together, they are not the same. IPD is a contracting method. This sets the rules for a project. Lean, on the other hand, is a mind-set. It's the mind-set you adopt on a project or in your daily work that focuses on the elimination of waste.

IPD is a building trend in design and construction communities. Many owners have heard about IPD and are requiring it for their projects. The American Institute of Architects (AIA) has developed a multi-party agreement that can be used to contractually join together several entities, rather than the traditional owner-architect agreement. The AIA has also published a guide on IPD that can be referenced for additional information.

Lean practices can be used on a project and are even valuable as a way to better manage your personal workload. The Lean Construction Institute (LCI) has formed Communities of Practice around the country that bring together Lean practitioners to develop skills and share knowledge within their business community.

Getting started

So, where does this all begin? As most things do, it starts at the very beginning of the project. The important part of an IPD project is that all of the major stakeholders are brought on board at the onset.This means the owner, architect, engineers, and major subcontracting partners are all involved at day one. This enables everyone involved with the lifecycle of the building to have a voice. Whether a project uses a formal multi-party contract or a standard contract, the spirit of collaboration is very important insetting the rules for how all of the parties will interact.

At the heart of collaboration is trust. This is often an uncomfortable place to start as a project team because we all bring our past experiences with us and worry that something bad will happen again. That is how most designers build their library of specification modifications and details. It is a way to manage a past problem and ensure that it will not get repeated. In an IPD environment, it is important to get the voice of all the players to guide decision making so you can ensure that the reason for a decision matches the goals of the project.


The electrical engineer has laid out the electrical rooms to show all of the equipment and to verify the size of the room for the architect during its initial floor plan layout. During a meeting with the owner's team, the electrical team finds that the adjacent room needs to grow larger, but the engineer is concerned about giving up space. The contractor suggests the use of an integrated switchgear system that could consolidate the equipment into a smaller footprint. Still, the engineer is concerned about designing for this without input from a manufacturer.

In a traditional process, identifying a single manufacturer (sole sourcing) is a practice that is discouraged. There is a fear of losing a competitive pricing opportunity with only a single manufacturer. In an IPD environment, the pricing is open to the entire team. Involving suppliers in the process allows for a design to be developed around the dimensions of that specific product.Suppliers are also a good resource in assisting to manage the budget amount and can help the team better understand the alternate options their product offers. In a traditional process, a change in manufacturer can often result in expensive modifications to constructed work and schedule delays to get equipment to fit within a space.

Work share

Another aspect of collaboration is work share. This can take on many levels of involvement, from sharing ideas to collaborative production of construction documents. Every project is different, and the team should start by identifying what each player's strengths are and how best to apply them to the project. If you think of the Lean principle of eliminating waste, focus on the elements of the project that can be streamlined.

Extreme collaboration can involve a coordinated effort between the engineer and contractor to produce a single document that is used for permitting and construction. In a traditional process a lot of time is involved with duplicating information. An engineer will design and draw the systems and then transfer them to the contractor to redraw the entire system for fabrication. When these processes are combined,waste in the form of duplicated effort is eliminated from the process.


During construction documents, the mechanical engineer draws the ductwork for the supply air on the floor. After the documents are complete, the fabricator looks at the design drawings and finds that there would be a more efficient way to connect the diffusers in a space that would result in far fewer fittings.

In a traditional process, this occurs on most every job with different avenues for resolution. Inmost cases, a compromise is made. By using the teams' best resources, these situations can be identified prior to completion of the design work. Including the sheet metal fabricator as a part of the team during development of the HVAC design ensures that the duct routing is efficient, meets all of the design criteria, and preps the construction team

<< First < Previous 1 2 Next > Last >>

No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Commissioning lighting control systems; 2016 Commissioning Giants; Design high-efficiency hot water systems for hospitals; Evaluating condensation and condensate
Solving HVAC challenges; Thermal comfort criteria; Liquid-immersion cooling; Specifying VRF systems; 2016 Product of the Year winners
MEP Giants; MEP Annual Report; Mergers and acquisitions; Passive, active fire protection; LED retrofits; HVAC energy efficiency
Driving motor efficiency; Preventing Arc Flash in mission critical facilities; Integrating alternative power and existing electrical systems
Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
Designing generator systems; Using online commissioning tools; Selective coordination best practices
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.