Let’s discuss the copper

Data center owners are opting for even larger servers, adding even more copper.

06/20/2012


Last week, we discussed the differences in construction costs and copper requirements between the competing approaches of locating medium-voltage transformations outdoors, and connecting the secondary loads via large underground duct banks, versus moving the transformations indoors, in close proximity to the loads.

 

Image of multiple duct banks with 12 4'' conduits. Courtesy: Joe Guentert 

 

The differences between the two approaches are becoming more pronounced recently, as more and more data center owners are opting for 230 V servers, and are distributing large critical power at 415 Y/240 V. That necessitates a full-size (and sometimes, an OVERSIZED) neutral, which adds at least another third to the tonnage and the cost of the copper in secondary feeders. I have seen some very large data center designs on the boards recently that will have more than 4 million lbs of copper in underground duct banks or cable tray, just to get 600, 480, or 415 V utility power and generator power into the low-voltage main distribution switchgear lineups, before the power is even distributed to any loads.

 

Some large data center owners who are moving to modular containers in their centers also have moved to switchgear containers and skid-mounted unit substations outdoors, close-coupling the transformations to the secondary switchgear. That removes all the copper between the transformer and the switchgear, but then adds back even MORE copper on the distribution feeders from the switchgear into the loads.

           

I’ve seen “modular” projects recently where the secondary switchgear was located outdoors, close-coupled to substation transformers, eliminating the need for a 4000 A or so secondary duct banks into the building. But those 4000 A trunk feeders were then replaced by branch distribution feeders in duct banks or cable tray having a total aggregate ampacity of 10,000 A or more, to distribute to the loads.

 

Image of multiple duct banks with 16 4'' conduits. Courtesy: Joe Guentert

 

I think that this pronounced trend of load growth cries out more loudly than ever before in history for a real and true “loadcenter” approach, with the transformations located right down in the center of the loads, where little 4000 A braided flex links like these, connecting a transformer to its secondary switchgear, can replace all those duct banks and hundred of tons of copper.

 

Image of 4000 A braided flex links, connecting a transformer to its secondary switchgear. Courtesy: Joe Guentert

 

If you can accept that this makes sense, what are the options? Until fairly recently, almost all of the loadcenter substation transformers that went inside data centers since 1995 were either VPI dry-type or epoxy cast coil construction.



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
High-performance buildings; Building envelope and integration; Electrical, HVAC system integration; Smoke control systems; Using BAS for M&V
Pressure piping systems: Designing with ASME; Lab ventilation; Lighting controls; Reduce energy use with VFDs
Smoke control: Designing for proper ventilation; Smart Grid Standard 201P; Commissioning HVAC systems; Boilers and boiler systems
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Consulting-Specifying Engineer case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
Integrating BAS, electrical systems; Electrical system flexibility; Hospital electrical distribution; Electrical system grounding
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.