Stop & Shop

Project Profile: Stop & Shop



Firm name: WD Partners

Project building name and location: Stop & Shop, Torrington, Conn.

Type of building and type of project: Grocery Store, New Constuction

Project completion date and project duration: November 2011

Engineering challenges and solutions:


Incorporating fuel cell design (UTC Purecell 400 KW) into the store, taking the store off the electrical grid, providing as much as 90+% of the electricity requirements and as much as 70% of the facility space heating requirements through the Fuel Cell.


Solutions:

 

Collaborating with Stop & Shop’s engineer, utilizing the fuel cell to power refrigeration and essential power loads and utilizing the waste heat (by-product of the fuel cell) for the hot water to provide hydronic heating and cooling (absorption chiller).

 

 