Time, material savings mean cost savings

Below is an example of how saving time and money on materials can translate to overall savings when wiring wire motor starters, contactors, and pilot devices.

08/13/2013


Many people say, “Time is money.” However, material is too. When it comes to engineering, assembling, and testing control panels, reducing either time or materials (or both) can reduce costs significantly. Here are two examples that illustrate how reducing time and materials can also reduce costs. 

In the time reduction example, the estimated time to wire motor starters, contactors, and pilot devices is 4 hours and 29 minutes. However, the estimate is only 41 minutes if a device-level wiring system is used—an 85% reduction in wiring time. Engineering and testing times were also reduced.

Courtesy: Eaton

In the material reduction example, an installation that consisted of 1,600 motor starters would have required 7.83 miles of control wiring. However, by using a device-level wiring system, only 0.45 mile of flat cable was used. Calculating the material cost of each method using $0.61/ft for flat cable and $0.14 for #14 AWG, the device-level wiring system saved more than $4,300. In addition, the calculated savings for wiring/assembly time was 22 man-days.

Courtesy: Eaton

Another significant benefit is the device-level wiring network allowed the system to be installed and commissioned without having to ring out a multitude of control wiring connections. This type of control system can also connect electronic motor starters to the system, which allows motor current and other loads to be monitored without having to add current transformers or analog input cards to the PLC. This feature could enable a higher level of predictive data monitoring that was prohibitively expensive in the past.

This article appears in the Applied Automation supplement for Control Engineering and Plant Engineering



Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
How to use IPD; 2017 Commissioning Giants; CFDs and harmonic mitigation; Eight steps to determine plumbing system requirements
2017 MEP Giants; Mergers and acquisitions report; ASHRAE 62.1; LEED v4 updates and tips; Understanding overcurrent protection
Integrating electrical and HVAC for energy efficiency; Mixed-use buildings; ASHRAE 90.4; Wireless fire alarms assessment and challenges
Power system design for high-performance buildings; mitigating arc flash hazards
Transformers; Electrical system design; Selecting and sizing transformers; Grounded and ungrounded system design, Paralleling generator systems
Commissioning electrical systems; Designing emergency and standby generator systems; VFDs in high-performance buildings
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Fire & Life Safety Engineer; Technip USA Inc.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me