Springfield Regional Medical Center

New construction: Springfield Regional Medical Center; Dynamix Engineering Ltd.

08/09/2012


This is an exterior rendering of the Springfield Regional Medical Center. Courtesy: Dynamix Engineering Ltd. (Click to enlarge)Project name: Springfield Regional Medical Center

Location: Springfield, Ohio

Firm name: Dynamix Engineering Ltd.

Project type, building type: New construction, hospital

Project duration: 2.5 years

Project completion date: Dec. 7, 2011

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $67.5 million

Engineering challenges

The firm had to complete the project utilizing an accelerated schedule, without change orders, and on budget. We had to design a sustainable and energy-efficient environment.

Solutions

The firm completed the project two months ahead of schedule with zero infectious control issues. The project was completed with 0.3% mechanical, electrical, plumbing, and technology change orders. The project also was completed under budget. The firm implemented a sustainable and energy-efficient environment, and used the ASHE Green Guide as a checklist.

Additional information

View a brochure on the Springfield Regional Medical Center.



Product of the Year
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
40 Under Forty: Get Recognized
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
MEP Giants Program
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
September 2018
Power boiler control, Product of the Year, power generation,and integration and interoperability
August 2018
MEP Giants, lighting designs, circuit protection, ventilation systems, and more
July 2018
Integrating electrical and HVAC systems, emerging trends in fire, life safety, ASHRAE 90.4
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
Data Center Design
Data centers, data closets, edge and cloud computing, co-location facilities, and similar topics are among the fastest-changing in the industry.
click me