Snowmelt system controls adjusted to save energy

At this large office campus, the sidewalk snowmelt system had never been reviewed or commissioned.

12/27/2013


During a recent retro-commissioning investigation for a large office complex, exp U.S. Services learned that the boiler-heated glycol system used for snow melting ran continually whenever the outdoor air temperature was below 38 F. NOAA weather records revealed that while the temperature is below 38 F for about 2250 hours/year, the actual amount of time of snowfall is only 580 hours/year. This difference of about 1700 hours represents the time the snowmelt system is on when it doesn’t need to be.

Because large areas were covered by eight different snowmelt systems, the calculated annual savings was 43,000 therms of natural gas and $21,000. This system was installed many years before the popularity of commissioning, but this speaks to the need for retro-commissioning, and/or at least a periodic review of control sequences and operations. 


Terrence Malloy is project manager for the energy solutions group at exp US Services Inc. He focuses on energy conservation, retro-commissioning, and renewable energy systems.

See more information on commissioning testing and standards below.



Product of the Year
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
40 Under Forty: Get Recognized
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
MEP Giants Program
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
May 2018
40 Under 40 winners, fire and life safety, performance-based designs, and more
April 2018
VRFs, lighting controls, BIM coordination, and more
March 2018
Sizing water pipes, ASHRAE 90.1, recovering waste heat, and more
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me