Seasonal Equipment Beats Permanent's Payback

What began as a one-time summer rental is moving into its sixth season. In 1996, Toyota Motor Manufacturing in Georgetown, Ky., began renting chillers to maintain its assembly plant at 79°F. Five air-cooled chillers with a total 1,500 tons of capacity took the heat and humidity out of the ambient summer air.

06/01/2001


What began as a one-time summer rental is moving into its sixth season. In 1996, Toyota Motor Manufacturing in Georgetown, Ky., began renting chillers to maintain its assembly plant at 79°F. Five air-cooled chillers with a total 1,500 tons of capacity took the heat and humidity out of the ambient summer air.

Eventually plant managers undertook an analysis, the results of which showed that using the rental chillers for peak summer loads was more cost-effective than adding to the 25,000-ton permanent water-cooled chiller capacity.

With 7,800 team members working on two shifts five days per week, "we performed load calculations using the most current weather patterns, and determined that we would need an additional 2,500 tons of chiller capacity," says Gary Van Corp, a mechanical specialist for Toyota. "By using air-cooled rental chillers, we eliminated the need for adding cooling-water piping connections and temporary containment areas for a water-cooled system."

For three years, the company rented seven 2,500-ton chillers. Then, Toyota added 2,000 tons of permanent chiller capacity, but still rented five 300-ton-capacity units in 1999 and 2000. The annual rental period runs from mid-June through August, the time of peak summer power loads.

From Pure Power, Summer 2001.





Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
How to use IPD; 2017 Commissioning Giants; CFDs and harmonic mitigation; Eight steps to determine plumbing system requirements
2017 MEP Giants; Mergers and acquisitions report; ASHRAE 62.1; LEED v4 updates and tips; Understanding overcurrent protection
Integrating electrical and HVAC for energy efficiency; Mixed-use buildings; ASHRAE 90.4; Wireless fire alarms assessment and challenges
Power system design for high-performance buildings; mitigating arc flash hazards
Transformers; Electrical system design; Selecting and sizing transformers; Grounded and ungrounded system design, Paralleling generator systems
Commissioning electrical systems; Designing emergency and standby generator systems; VFDs in high-performance buildings
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Fire & Life Safety Engineer; Technip USA Inc.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me