Renewables focus new interest on regional transmission

Transmission line access is emerging as a major roadblock to greater development of renewable energy resources, and legislators at the state and federal levels are considering new proposals to streamline approval processes.

09/01/2008


Transmission line access is emerging as a major roadblock to greater development of renewable energy resources, and legislators at the state and federal levels are considering new proposals to streamline approval processes.

More than 25 states now have renewable portfolio standards (RPS) in place that require electric utilities to purchase a percentage of the power they sell to consumers from renewable resources. The definitions of “renewable” differ among the states, but they all include wind and solar power among acceptable technologies. In some states, utilities will be expected to provide up to 20% of their electricity from renewable sources by 2020. The lack of transmission-line access to these often-remote resources is causing many providers to question the attainability of such goals.

In fact, up to 60 gigaW of new renewable capacity will need to be developed by 2025 if states are to meet current RPS goals, according to a study released in April by the Lawrence Berkeley National Laboratory. More than 93% of nonhydroelectric renewable capacity added since 1998 has come from wind power, said the authors of “Renewables Portfolio Standards in the United States.” Many of the best locations for wind-power generation are not served by existing transmission lines, raising the call for a coordinated approach to new development efforts.

The National Energy Policy Act of 2005 is addressing transmission congestion. The U.S. Dept. of Energy and the Federal Energy Regulatory Commission have been given power to declare national interest energy transmission corridors, within which federal authorities may be able to provide construction permits for especially contentious projects. Now some areas are considering similar corridors for areas where renewable energy might be especially plentiful.

The Western Governors Assn., which represents the interests of 19 states, kicked off the Western Renewable Energy Zones Project in May. The initiative aims to identify regional renewable energy districts and encourage development of transmission capacity to reach these areas. Two Canadian provinces and areas of Mexico that also are connected to the Western Interconnection also are participating.

Building on this effort, Sen. Harry Reid (R-Nevada) proposed legislation this spring authorizing federal renewable energy zones, where renewable sources could generate at least 1,000 MW. The bill would provide new financing options for building transmission lines needed to connect those resources.

At the opposite end of the country, Maine regulators are taking a comprehensive look at that state’s transmission system, spurred by interconnection requests by developers to add up to 1,250 MW of wind-power capacity to the state’s grid. Maine’s transmission system has been declared maxed out by regulators, so new project developers have no way to get their power to market. Proposed line upgrades would enable that electricity to serve the entire New England grid. One of the proposed projects would add up to 400 wind turbines, and 800 MW of capacity to Aroostook County, at the state’s northernmost point.





Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Exploring fire pumps and systems; Lighting energy codes; Salary survey; Changes to NFPA 20
How to use IPD; 2017 Commissioning Giants; CFDs and harmonic mitigation; Eight steps to determine plumbing system requirements
2017 MEP Giants; Mergers and acquisitions report; ASHRAE 62.1; LEED v4 updates and tips; Understanding overcurrent protection
Power system design for high-performance buildings; mitigating arc flash hazards
Transformers; Electrical system design; Selecting and sizing transformers; Grounded and ungrounded system design, Paralleling generator systems
Commissioning electrical systems; Designing emergency and standby generator systems; VFDs in high-performance buildings
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Fire & Life Safety Engineer; Technip USA Inc.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me