Project in Progress: Apex Friendship Middle School March 2018 update

The project is on track for its grand opening in August.

03/27/2018


Figure 1: Aerial photos of the Apex Friendship Middle School’s construction progress. Courtesy: DewberryThe Apex Friendship Middle School is on track to complete construction this July, and the school is on schedule for its grand opening in August. The school will accommodate up to 1,280 students.

General work:

 

  • Windows are being installed.
  • Flooring is being installed in various locations of Areas architecture, construction, and design.
  • Painting is being performed in various locations.
  • Ceramic tile installation is in progress.
  • Casework is being installed in various locations.
  • Windows and frames are being installed.
  • Site installation in progress.
  • Drywall installation is near completion in Area B.
  • Ceiling installation is in progress.

Figure 2: Aerial photos of the Apex Friendship Middle School’s construction progress. Courtesy: DewberryMechanical, electrical, and plumbing

  • Plumbing fixture installation has started in some areas of the building.
  • Air handling units are starting to come online with initial startups.
  • Electrical panels are set and wiring is in progress.
  • Mechanical ductwork and hydronic piping insulation installation is in progress throughout.
  • Fire sprinkler piping and equipment installation is in progress throughout.


Product of the Year
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
40 Under Forty: Get Recognized
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
MEP Giants Program
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
May 2018
40 Under 40 winners, fire and life safety, performance-based designs, and more
April 2018
VRFs, lighting controls, BIM coordination, and more
March 2018
Sizing water pipes, ASHRAE 90.1, recovering waste heat, and more
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me