Power Factor No Longer a Factor for Pipe Manufacturer

An East Texas pipe manufacturer recently experienced some unexpected consequences from its modernization efforts. Managers at the company's fabrication plant, which flattens steel ingots to pipe-wall thickness, had replaced its old single-speed motor-generator sets with variable-speed drive models. The move meant greater control over the massive rolling mills, but it also resulted in current su...

12/01/2003


An East Texas pipe manufacturer recently experienced some unexpected consequences from its modernization efforts. Managers at the company's fabrication plant, which flattens steel ingots to pipe-wall thickness, had replaced its old single-speed motor-generator sets with variable-speed drive models. The move meant greater control over the massive rolling mills, but it also resulted in current surges when ingots entered one of the large machines. The surges, in turn, caused voltage sags of up to 8% on the 13.8-kV bus of the plant's motor room.

In addition to forcing nuisance tripping of other motors connected to the affected bus, these conditions also resulted in poor power-factor conditions for the entire facility. With a peak reactive power demand of almost 11 MVAR, VAR compensation was required.

Several options were considered, including fixed capacitors, an inverter-based compensator and a capacitor-based compensator. Fixed capacitors were seen as a less costly but also less complete solution, because of ongoing losses associated with capacitors always being in the circuit. In addition, these units weren't seen as capable of handling large reactive-power swings associated with the range of mill motors operating. Managers realized inverter-based compensators could handle these swings, but thought them too expensive for their needs.

A 5,000-kVAR capacitor-based compensator was the chosen option. The unit offered a 2-1/2-year payback, compared to the assumed 6-1/2-year payback of the inverter-based solution. In addition, the selected unit was more compact, allowing for closer installation to the affected mill.

The compensator was installed in January 2000 and has maintained voltage variation within +/-3.2% of nominal. Power factor is now typically above 92%, and total voltage and current harmonic distortion are now less than 10% and 5%, respectively.





Product of the Year
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
40 Under Forty: Get Recognized
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
MEP Giants Program
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
May 2018
40 Under 40 winners, fire and life safety, performance-based designs, and more
April 2018
VRFs, lighting controls, BIM coordination, and more
March 2018
Sizing water pipes, ASHRAE 90.1, recovering waste heat, and more
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me