Leaning into IPD: A primer for engineers: definitions

Integrated project delivery (IPD) is aimed at more directly connecting what the end users are expecting to get and what actually gets built for them, while at the same time minimizing lifecycle costs and shortening the overall schedule.

10/31/2018


Traditional design-bid-buildDesign-bid-build (D-B-B) is a traditional delivery method in which the owner enters into an agreement with an architecture and engineering (AE) team to design and document the systems required for their building and enters into a separate agreement with a contractor to furnish and install the equipment and materials that comprise those systems. The AE team stamps and seals the basis of design/calculations, plans, and specifications while the contractors bid the documents and subsequently develop submittals followed by furnishing/installing the work (Figure 2).

Design-assist (D-A) is a less traditional, hybrid sort of delivery method that mirrors the D-B-B delivery method except that the contractor takes some design and documentation responsibilities for subsystems and also provides continual feedback on alternatives that can improve value to the owner (Figure 3).

Design-build (D-B) is a less traditional delivery method that has been implemented for the past few decades in which the owner hires a single entity that is responsible for designing, documenting, furnishing, and Design-build, design-assist, IPD lightinstalling everything necessary for the required systems. In many cases, the owner hires the contractor and the contractor, in turn, hires the AE team. The AE team still stamps and seals the basis of design/calculations, plans, and specifications while the contractors develop submittals followed by furnishing/installing the work. However, the contractors don't need to bid the documents because they've been pricing and buying the work throughout the process (Figure 3).

Integrated project delivery (IPD) is a relatively new delivery method that aims to improve collaboration to increase value by using an incentivized risk-reward form of tri-party agreement. IPD requires that a team be able to move beyond reactive coordination into proactive integration. IPD is not for every project; the benefits of IPD increase as the scale and/or complexity of a renovation or new construction project increases. Like with design-build, the AE team stamps and seals the basis of design/calculations, plans, and specifications. The contractors develop submittals followed by furnishing/installing the work; however, the contractors don't need Integrated project deliveryto "hard-bid" the documents because they've been pricing and buying the work throughout the process. There is a school of thought that suggests owners have demanded this type of incentivized delivery method to move beyond the traditional yet confrontational, wasteful construction process that has typically led to cost overruns, schedule extensions, and unmet owner expectations (Figure 4).

Integrated project delivery (IPD)-light is not a formal delivery method; it is a commonly used term that tends to be synonymous with design-assist (Figure 3).

Value is defined as quality plus performance divided by lifecycle cost plus schedule. Some teams may choose to use first cost instead of lifecycle cost (lifecycle cost tends to be used for owner-occupied facilities that are more complex in their design and operation, such as labs or hospitals).


Laurence V. Wilson is a principal at SmithGroup. He has more than 3 decades of experience in the field of building system engineering, including analysis, planning, design, and construction administration.

 



Product of the Year
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
40 Under Forty: Get Recognized
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
MEP Giants Program
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
November 2018
Emergency power requirements, salary survey results, lighting controls, fire pumps, healthcare facilities, and more
October 2018
Approaches to building engineering, 2018 Commissioning Giants, integrated project delivery, improving construction efficiency, an IPD primer, collaborative projects, NFPA 13 sprinkler systems.
September 2018
Power boiler control, Product of the Year, power generation,and integration and interoperability
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
Data Center Design
Data centers, data closets, edge and cloud computing, co-location facilities, and similar topics are among the fastest-changing in the industry.
click me