Kravis Deck with open circulation, natural daylight, and shading. Courtesy: IBE Consulting Engineers (Click to enlarge)Project name: Kravis Center at Claremont McKenna College

Location: Claremont, Calif.

Firm name: IBE Consulting Engineers 

Project type, building type: New construction, school (college, university)

Project duration: 3 years

Project completion date: Jan. 11, 2007

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $15.5 million

Engineering challenges

The building has a gross area of 82,000 sq ft and includes a basement with a parking garage and four levels above grade. The challenge was providing a flexible solution for all the program elements, including a server room, classrooms, offices, support spaces, and circulation areas.

Solutions

Classroom with natural daylight and radiant ceilings. Courtesy: IBE Consulting Engineers (Click to enlarge)Offices are provided with active beams in the overhead plenum to each space. One hundred percent outside primary air is supplied from air handling units located in the basement. Classrooms are provided with a hybrid air-radiant system combining overhead air distribution with radiant panels. There are two air-handling units for the hybrid system located in the basement. The radiant system provides both heating and cooling. There is a dedicated 100% outside air distribution for the spaces with radiant ceilings. The other spaces have demand-controlled ventilation. Additionally, we employed several tactics to increase the building's performance and to exceed Title 24 minimum standards by 37.9 percent and ASHRAE 90.1 by 46%: high-performance lighting systems in classrooms, seminar rooms, meeting rooms, and offices, with occupancy sensors and daylight harvesting sensors; high-performance glazing; high-efficiency frictionless chillers; wall insulation increased to R-19 and roof insulation increased to R-30; and daylight harvesting sensors.



Product of the Year
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
40 Under Forty: Get Recognized
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
MEP Giants Program
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
July 2018
Integrating electrical and HVAC systems, emerging trends in fire, life safety, ASHRAE 90.4
June 2018
Chilled-water system design, NFPA 99, Grounded power supply systems
May 2018
40 Under 40 winners, fire and life safety, performance-based designs, and more
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
Data Center Design
Data centers, data closets, edge and cloud computing, co-location facilities, and similar topics are among the fastest-changing in the industry.
click me