How to design a grounded power supply system

Transformerless uninterruptible power supply (UPS) systems operate ungrounded during power transfer to a backup source, but a robust grounding design can accommodate the requirement of both grounded and ungrounded systems.

06/20/2018


Learning objectives: 

  • Understand the difference between grounded and ungrounded systems.
  • Learn what the code requires of ungrounded ac and dc power systems.
  • Know how the behavior of ungrounded systems during ground faults differs from that of grounded systems, and how to mitigate this effect.

In any facility containing critical loads, whether related to life safety or sensitive computer loads vital to facility operation, one of the most important pieces of equipment specified in the design is the uninterruptible power supply (UPS), which uses stored energy to supply power to these critical loads when normal power is lost and a backup power source is starting up to supply the building loads.

When selecting UPS modules to power critical loads in a facility, one key decision to make is whether to use a UPS with or without input and/or output transformers. See Figures 2 and 3 for notional diagrams depicting a transformer-based and a transformerless UPS module, respectively.

Over the last decade, transformerless UPS systems have grown rapidly in popularity, eclipsing transformer-based designs. This transition is not surprising, as transformerless modules offer many advantages over a UPS with transformers. The largest advantage is efficiency. A UPS without transformers can see efficiency advantages of 5% or greater, as compared with those with transformers. Not only does this mean lower electricity bills, but it also represents lower heat loads in the room housing the UPS, resulting in reduced HVAC requirements.

In facilities with a large amount of critical load, the savings can be dramatic. Additionally, transformerless UPS systems reduce the weight and footprint of each UPS module when compared with transformer-based systems, reducing the size and structural requirements of electrical rooms and leaving more room for white space or other portions of the building.

However, the output transformer of a transformer-based UPS does provide an option that is not available for transformerless UPS systems: The electrical isolation provided by a transformer gives the opportunity to create a separately derived neutral-to-ground connection at the output of the UPS. In certain situations—such as a system served by an ungrounded delta service, a service grounded through a high-resistance ground, or systems in which there is the potential that the two sources of a dual-input UPS may come from two independent sources—it may be desirable to derive a neutral at the UPS without a transformer, to provide the UPS with a stable ground reference that it can use for voltage regulation at its output and on its dc bus.

If such a neutral is not derived in a transformerless UPS system, then while the UPS battery is discharging during an input power failure and the UPS input circuit breaker is open, the downstream system is operating ungrounded. In most installations, there will be one or more downstream transformers, external to the UPS, served by the critical power system. These downstream transformers are usually housed in a power distribution unit, and on their secondary side a grounded system can be derived, but that portion of the system on the primary side will nonetheless be ungrounded during this period.

Most design engineers are used to working with grounded systems, and the prospect of leaving a portion of the building ungrounded, even during a generally brief transition period between input power failure and the facility backup power system starting up, may seem worrisome. However, creating a safe, robust, and code-compliant ungrounded power system is relatively simple, requiring only minor modifications from the grounding and bonding systems required in any grounded power system. 

Grounded versus ungrounded

Figure 1: The Bexar Metro 911 Network District Regional Operations Center in San Antonio, Texas, is a 2-story building that houses an emergency call center. Courtesy: Dror Baldinger FAIA, Architectural Photography LLCTo understand the special requirements of an ungrounded system, it is important to first define what is meant by "grounded" and "ungrounded." System grounding is achieved by intentionally connecting a current-carrying conductor to the ground (i.e., the earth) or to something that serves in place of the ground. Usually, this is achieved by connecting the system's neutral wire to the ground at the supply source, often the wye-connected secondary side of a transformer or the stator of a generator, as well as at the main service-disconnecting means of the facility. Therefore, an ungrounded system is one in which none of the current-carrying conductors are intentionally connected to the ground.

Grounded systems are typically preferred to ungrounded systems for several reasons. Grounded systems stabilize voltage levels throughout the system, ensuring that all equipment in the system operates under the same potential difference. This is particularly important for a UPS, as it is tasked with precisely regulating voltage levels both at its output and on its dc bus, and accurate voltage regulation requires a solid, stable reference to ground to maintain. Grounded systems also mitigate voltage spikes due to lightning strikes, help prevent potential differences between different pieces of equipment in the system, and provide a circuit for ground-fault current to flow through the grounded circuit conductors back to the supply source, allowing overcurrent protective devices to quickly operate and isolate the fault.

NFPA 70: National Electrical Code (NEC), Article 250.4, provides general, performance-based requirements for both grounded systems in 250.4(A) and ungrounded systems in 250.4(B). Grounded systems have five requirements: electrical system grounding, grounding of electrical equipment, bonding of electrical equipment, bonding of electrically conductive materials, and effective ground-fault current paths.

Notably, the four requirements of ungrounded systems listed in 250.4(B) are similar or identical to the latter four requirements of grounded systems. Just as in grounded systems, ungrounded systems require that noncurrent-carrying conductive materials enclosing electrical conductors or equipment, and those that are likely to become energized, be connected to the ground through a low-impedance path. The overlap between these two sets of requirements illustrates the notion that designing an ungrounded system is not too terribly different than designing a grounded one.

Figure 2: This shows a conceptual single-line drawing of a transformer-based uninterruptible power supply (UPS). A neutral is derived at the secondary connection of the output transformer. Courtesy: Page Inc.To understand what the NEC requires of a transformerless UPS system when it is operating ungrounded during battery discharge, we must first identify how this system is defined using the language of the NEC. When the UPS input circuit breaker is open, the UPS is not connected to the upstream power system, and therefore to the supply service, through any circuit conductors other than those used for grounding and bonding.

It is important to note that even though the UPS enclosure and downstream equipment may still be effectively bonded to the supply-source enclosure in this condition, the system is not considered grounded unless a current-carrying conductor is connected to ground. Therefore, the NEC defines the system in this state as a separately derived system and the UPS batteries as a separately derived source. The grounding requirements for ungrounded separately derived systems are defined in Article 250.30(B).

This section of the NEC requires three components: grounding electrode conductor, grounding-electrode system, and supply-side bonding jumper. The latter of these components is only required when the source of a separately derived system is located in a separate enclosure than the first disconnecting means. This will usually not be the case for a UPS, as the output circuit breaker of the UPS is normally housed in the UPS enclosure.

All three of these grounding components are required in grounded separately derived systems as well. Essentially, the UPS enclosure must be connected to ground through the building's grounding-electrode system by way of a grounding electrode conductor. This connection in an ungrounded system serves as the grounding reference point for all conductive equipment in the ungrounded system that does not carry current under normal conditions. 

Figure 3: In this conceptual single-line drawing of a transformerless uninterruptible power supply (UPS), a neutral cannot be derived at the output of the inverter without a transformer. Courtesy: Page Inc.Grounding the system

UPS manufacturers have a variety of solutions for the issue of how to ensure the UPS maintains a reference to the ground during ungrounded conditions, to ensure that the UPS voltage regulation remains stable. Some manufacturers derive a so-called "virtual ground" at the common point of the input and output filters of the UPS to achieve this purpose. This is often a standard feature, especially on newer UPS models, but an optional accessory is required in some cases. When specifying a transformerless UPS, especially in a 3-phase, 3-wire system, take care when considering how it will operate under ungrounded conditions.

The rules governing the grounding-electrode system and grounding electrode conductors are found in Part III of Article 250 of the NEC. The same grounding-electrode system used for the building as a whole must also be used for any separately derived systems, as per NEC 250.58, so all that is required is a connection between the building's grounding electrode and the UPS enclosure through a grounding electrode conductor. Accordingly, all of the normal requirements for grounding-electrode system materials listed in NEC 250.52 and installation listed in 250.53 apply in this situation.

Similarly, the rules governing grounding electrode conductors are not different between grounded and ungrounded systems. NEC Articles 250.62 and 250.64 govern the materials and installation methods of grounding electrode conductors, respectively. The required size of the grounding electrode conductors used must be determined through the requirements of NEC 250.66, which vary based on the type of grounding electrode used, the size of the largest ungrounded conductor or set of conductors in the system, and the material of the grounding electrode conductor.

No matter the size of the system, the grounding electrode conductor must always be at least as large as #8 AWG for copper or #6 AWG for aluminum, and unless superseded by local amendments or authority having jurisdiction (AHJ) requirements, the grounding electrode conductor is not required to be larger than #3/0 AWG for copper or 250 kcmil for aluminum. Finally, requirements for bonding grounding electrode conductors to the grounding-electrode system are covered in NEC 250.68. 


<< First < Previous Page 1 Page 2 Next > Last >>

Product of the Year
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
40 Under Forty: Get Recognized
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
MEP Giants Program
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
November 2018
Emergency power requirements, salary survey results, lighting controls, fire pumps, healthcare facilities, and more
October 2018
Approaches to building engineering, 2018 Commissioning Giants, integrated project delivery, improving construction efficiency, an IPD primer, collaborative projects, NFPA 13 sprinkler systems.
September 2018
Power boiler control, Product of the Year, power generation,and integration and interoperability
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
Data Center Design
Data centers, data closets, edge and cloud computing, co-location facilities, and similar topics are among the fastest-changing in the industry.
click me