Guidelines for applying PUE metric completed

The latest recommendations for energy efficiency measurement and reporting completes the guidelines for applying the Power Usage Effectiveness (PUE) metric.

06/06/2011


The Green Grid Association, together with The Data Center Metrics Coordination Taskforce, has announced its latest recommendations for energy efficiency measurement and reporting.

The new report, Recommendations for Measuring and Reporting Overall Data Center Efficiency: Version 2 – Measuring PUE at Data Centers, completes the guidelines for applying the Power Usage Effectiveness (PUE) metric, created and promoted by The Green Grid. The new information includes specific recommendations for how to measure and calculate PUE in mixed-use data center facilities and introduces a condenser water source energy weighting factor.

Alignment on these methodologies across the industry will lead to consistent and repeatable measurement strategies that allow data center operators to monitor and improve the energy efficiency when operating their existing data centers, or when designing new facilities. The task force’s latest report represents the combined decision-making from the 7x24 Exchange, ASHRAE, The Green Grid, Silicon Valley Leadership Group, U.S. Department of Energy’s Save Energy Now and Federal Energy Management Programs, U.S. Environmental Protection Agency’s ENERGY STAR Program, U.S. Green Building Council, and Uptime Institute.

The following principles were reportedly agreed to:

  • PUE, using source energy consumption, is the preferred energy efficiency metric for data centers.
  • When calculating PUE, IT energy consumption should, at a minimum, be measured at the output of the uninterruptible power supply (UPS). However, the industry will continue to improve measurement capabilities so that measurement of IT energy consumption directly at the IT load (e.g., servers, storage, network, etc.) becomes the common practice.
  • For a dedicated data center, the total energy in the PUE equation will include all energy sources at the point of utility handoff to the data center owner or operator. For mixed-use data centers, the total energy will be all energy required to operate the data center, similar to a dedicated data center, and should include cooling, lighting, and support infrastructure for the data center operations.

- Edited by Amanda McLeman, Consulting-Specifying Engineer, www.csemag.com



Product of the Year
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
40 Under Forty: Get Recognized
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
MEP Giants Program
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
July 2018
Integrating electrical and HVAC systems, emerging trends in fire, life safety, ASHRAE 90.4
June 2018
Chilled-water system design, NFPA 99, Grounded power supply systems
May 2018
40 Under 40 winners, fire and life safety, performance-based designs, and more
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
Data Center Design
Data centers, data closets, edge and cloud computing, co-location facilities, and similar topics are among the fastest-changing in the industry.
click me