"Owners are making changes that are revolutionizing the construction process," states a summary of the latest annual owner survey conducted by management consulting firm FMI and the Construction Management Assn. of America. Results of the sixth annual survey were presented at the CMAA National Conference in Huntington Beach, Calif.

10/01/2005


"Owners are making changes that are revolutionizing the construction process," states a summary of the latest annual owner survey conducted by management consulting firm FMI and the Construction Management Assn. of America.

Results of the sixth annual survey were presented at the CMAA National Conference in Huntington Beach, Calif. in September and found:

  • 66% use design-bid-build most often, but only 23% think this construction method offers the best value.

  • Between 40% and 50% of all construction projects are running behind schedule, and many feel that the blame lies in inefficiencies built into the way projects are managed.

  • The commissioning process runs longer than planned 47% of the time, partially due to the fact that many respondents said they don't have a formal commissioning requirement.

  • Only 37% of owners use standard contract documents provided by the AIA or other groups, while the majority uses their own modified or proprietary contracts.





Product of the Year
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
40 Under Forty: Get Recognized
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
MEP Giants Program
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
July 2018
Integrating electrical and HVAC systems, emerging trends in fire, life safety, ASHRAE 90.4
June 2018
Chilled-water system design, NFPA 99, Grounded power supply systems
May 2018
40 Under 40 winners, fire and life safety, performance-based designs, and more
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
Data Center Design
Data centers, data closets, edge and cloud computing, co-location facilities, and similar topics are among the fastest-changing in the industry.
click me