CDM Smith: Indianapolis Airport Electric Vehicle Charging

Electrical, power; vehicle charging station; and existing building retrofit

By CDM Smith August 9, 2018

Engineering firm: CDM Smith

2018 MEP Giants rank: 63

Project: Indianapolis Airport Electric Vehicle Charging

Location: Indianapolis, Indiana, United States

Building type: Electric vehicle charging station

Project type: Existing building retrofit

Engineering services: Electrical, power

Project timeline: June 2016 to December 2017

MEP/FP budget: $123,340

Challenges

The retrofit of the electric system to accommodate the electric vehicle charging infrastructure was a challenge for this project.

Solutions

CDM Smith’ssolution was to develop a detailed design using a preselected charging infrastructure vendor and to perform a detailed investigation of the existing infrastructure.