Carl R. Darnall Army Medical Center April update

Hospital level 1 is ready for furniture move-in. Hospital level 2 punchlist is underway.

By Southland Industries April 6, 2015

April 2015 update:

  • Hospital level 1 has been partially turned over to the client for furniture move-in.
  • Starting Hospital test-and-balance (TAB) for the bed tower (HL4-7).
  • Hospital telecom rooms have been turned over to the client for equipment delivery.
  • Hospital level 2 punchlist is underway. Beginning BSL3 point-to-point verification