Campus-style distribution with differing voltages

In this arrangement, the fire pump and service entrance voltages are not the same.

03/24/2016


Figure 3: Power feed to the fire pump as a part of a campus-style distribution is shown with the feed ahead of the service disconnection means. Courtesy: WSP + ccrdIn this example, the design team is working with multiple buildings, with each having an individual power feed from a 15-kV feeder loop around the campus. The 15-kV service is derived from the utility at a central energy plant and then feeds the 15-kV loop. Each building has a substation that transforms the power down to 480 V for distribution within the building. Each building also has a dedicated 480 V fire pump to support its sprinkler system.

The difficulty with this arrangement is that the fire pump and service entrance voltages are not the same. This prevents a direct connection to the fire pump. Thus, the designer will need to transform power to the pump utilization voltage, which can introduce overcurrent protection devices and disconnecting means. How these are configured and sized must meet the requirements of NFPA 70: National Electrical Code (NEC) 695.4(B).

When feeding through a transformer, the electrical engineer needs to design to the requirements of NEC 695.5. The normal power feed from the substation needs to include 125% of the load of the fire pump and its accessories in the calculation for the transformer. A transformer's primary overcurrent protection device should be capable of carrying the locked rotor amps of the fire pump and accessories, and a secondary overcurrent protection device downstream of the transformer should not be included for the fire pump feed. This will allow the fire pump to continue running and keep the fire protection system operational to protect the building and its occupants. Here are some key items to consider with this arrangement:

  • The overcurrent protection device should be sized to carry the lock-rotor current of the pump and its accessories indefinitely, as this is the primary source of power. This pump should continue running even during adverse conditions.
  • The overcurrent protection device serving the fire pump shall be selectively coordinated with the other devices to prevent a fault elsewhere in the system that would disable the fire pump.
  • All disconnecting means serving the fire pump and its accessories shall be clearly identified to prevent inadvertent disconnection of the power source.
  • Consideration should be given to the routing of the feeders so they are protected from physical harm or damage by fire.

The feeder from the switchgear to the fire pump controller (located in a different room) will be routed overhead and encased with 2 in. of concrete so that it is considered outside the building per NEC 230.6(2).

If the building is supported by a 15-kV distribution loop that is an "A/B"-type arrangement fed from separate utility substations, the designer could provide two feeds to the fire pump from this loop; one from each of the services as defined by NEC 695.3(C)(1). This should be coordinated with the authority having jurisdiction to validate that these two sources would then be considered as a reliable source.

 


Sarah Kuchera is senior vice president and electrical engineer at ccrd + WSP. Her duties have included project management, production coordination, and project engineering on a variety of different projects including hospital, retail, hospitality, and office buildings. 



Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
How to use IPD; 2017 Commissioning Giants; CFDs and harmonic mitigation; Eight steps to determine plumbing system requirements
2017 MEP Giants; Mergers and acquisitions report; ASHRAE 62.1; LEED v4 updates and tips; Understanding overcurrent protection
Integrating electrical and HVAC for energy efficiency; Mixed-use buildings; ASHRAE 90.4; Wireless fire alarms assessment and challenges
Power system design for high-performance buildings; mitigating arc flash hazards
Transformers; Electrical system design; Selecting and sizing transformers; Grounded and ungrounded system design, Paralleling generator systems
Commissioning electrical systems; Designing emergency and standby generator systems; VFDs in high-performance buildings
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Fire & Life Safety Engineer; Technip USA Inc.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me