Building commissioning challenges, solutions: Electrical, power system

Commissioning, recommissioning, or retro-commissioning, can be a challenge—and the more complex a facility is, the more boxes an engineer has to check to get the job done right. Electrical and power systems must be carefully commissioned to meet code and owner expectations.

08/31/2014


Ray Dodd, PE, CxA, LEED AP
, President, Total Building Commissioning Inc., PhoenixKyle G. Hendricks, LEED AP, Energy and sustainability consultant, Environmental Systems Design Inc., ChicagoDonald H. Horkey, PE, LEED AP, Principal, mechanical engineer, DLR Group, MinneapolisDavid J. LeBlanc, PE, FSFPE, Senior vice president, Rolf Jensen & Associates, Inc., Framingham, Mass.

Respondents:

  • Ray Dodd, PE, CxA, LEED AP
, President, Total Building Commissioning Inc., Phoenix
  • Kyle G. Hendricks, LEED AP, Energy and sustainability consultant, Environmental Systems Design Inc., Chicago
  • Donald H. Horkey, PE, LEED AP, Principal, mechanical engineer, DLR Group, Minneapolis
  • David J. LeBlanc, PE, FSFPE, Senior vice president, Rolf Jensen & Associates, Inc., Framingham, Mass.

Environmental Systems Design Inc. (ESD) identified low-cost and no-cost energy saving opportunities for the John Hancock Center’s base building HVAC systems, as well as 1,569,297 kWh of annual electricity savings through the implementation of nine low-cost retro-commissioning measures. Courtesy: ESDCSE: What’s the one commissioning issue most commonly overlooked in electrical/power systems?

 

Horkey: The commissioning of emergency backup generator systems is always a schedule and coordination challenge. It is critical that all parties be on-site to witness the commissioning of these systems. Oftentimes this commissioning activity will need to occur at night when the building is unoccupied to minimize disruption to building occupants.

Dodd: Communication between the emergency power system (generator, automatic transfer switch, UPS) and the BAS. What elements are supposed to be on emergency power are often left out of the design documents or poorly communicated. If the CxA doesn’t have both a mechanical and electrical background, those nuances can easily be missed.

CSE: How have energy-efficiency and sustainability requirements affected your approach to commissioning electrical systems?

Hendricks: A major piece of the energy and sustainability philosophy is metering, and we have seen an increase in the importance of submetering various equipment loads. Verifying meter calibration and confirming meter locations during design review are important steps in the commissioning process.

Dodd: Lighting is a huge consumer of electrical energy. Measurement and verification requires that loads (HVAC, plug, and lighting) are segregated along with metering and submetering are very helpful in determining what equipment in the building is using energy and how it is functioning. These requirements must be established in the design process as they are impossible to implement after construction starts. We focus our efforts on these energy-efficiency and sustainability requirements in the design to make sure commissioning goes smoothly in the acceptance phase of the project.

Horkey: The need for real-time data analysis has increased the need for measurement and verification requirements. These requirements typically lead to significantly more metering needs. The commissioning professional is ideally suited to ensure that the required metering instrumentation is included in the contract documents and is installed in the project.

CSE: If an owner is contemplating U.S. Green Building Council LEED certification or if ASHRAE 90.1-2010 compliance is required, the commissioning of lighting controls is a necessity. Describe a recent project in which you commissioned the lighting and related controls systems.

Dodd: We recently commissioned the lighting control system for a large financial services client in a high-rise building. The space used zoned open office space with private offices on the perimeter. The system was designed so that in the open office lighting levels are adequate for the localized users but not over-lit for the unused open office space. It was a complex sensing system and took several iterations of testing to get the programming right.



Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Exploring fire pumps and systems; Lighting energy codes; Salary survey; Changes to NFPA 20
How to use IPD; 2017 Commissioning Giants; CFDs and harmonic mitigation; Eight steps to determine plumbing system requirements
2017 MEP Giants; Mergers and acquisitions report; ASHRAE 62.1; LEED v4 updates and tips; Understanding overcurrent protection
Power system design for high-performance buildings; mitigating arc flash hazards
Transformers; Electrical system design; Selecting and sizing transformers; Grounded and ungrounded system design, Paralleling generator systems
Commissioning electrical systems; Designing emergency and standby generator systems; VFDs in high-performance buildings
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Fire & Life Safety Engineer; Technip USA Inc.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me