BRAC 133 Office Towers

Existing building retrofit: BRAC 133 Office Towers; Sebesta Blomberg

08/09/2012


BRAC 133 at Mark CenterProject name: BRAC 133 Office Towers

Location: Arlington, Va.

Firm name: Sebesta Blomberg

Project type, building type: Existing building retrofit, office

Project duration: 2.7 years

Project completion date: Sept. 15, 2011

Engineering challenges

This fast-track design-build project required an intense level of rigor from Sebesta Blomberg. High-end security systems, state-of-the-art HVAC strategies, and complex building automation systems were thoroughly tested while accommodating a compressed schedule. More than 1,500 functional performance tests were developed, conducted, and tracked to completion to ensure that building systems operate effectively. Aggressive scrutiny was applied to key components, such as central plant heating/cooling systems, data centers, building control centers, and emergency electrical systems.

Solutions

Sebesta Blomberg drew on its national corporate presence and assembled an experienced team to accommodate the demanding schedule and extraordinary scope of work. Equipment and systems were tested as they became available. Unparalleled flexibility and clear communication lines were required and established with project stakeholders. Construction completion and full complex operation were achieved one month ahead of schedule.



Product of the Year
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
40 Under Forty: Get Recognized
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
MEP Giants Program
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
May 2018
40 Under 40 winners, fire and life safety, performance-based designs, and more
April 2018
VRFs, lighting controls, BIM coordination, and more
March 2018
Sizing water pipes, ASHRAE 90.1, recovering waste heat, and more
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me