ASTM International Standards Provide Blueprint for Inspecting Firestop

08/04/2005


Firestop systems have become essential components in saving lives and minimizing property damage during a fire. Because the installation of a firestop system is a very exacting, zero-tolerance process, it is imperative that the post-installation inspection of a firestop system also be exacting.

Two American Society of Testing and Materials (ISTM) International standards developed by ASTM Committee E06 on Performance of Buildings are now important components in the accurate inspection of firestop systems.

The first of the two standards, E 2174, Practice for On-Site Inspection of Installed Fire Stops, was first approved in 2001. The purpose of this practice is to establish procedures to inspect penetration firestop systems. The second standard, E 2393, Practice for On-Site Inspection of Installed Fire Resistive Joint Systems and Perimeter Fire Barriers, was approved in 2004. The purpose of E 2393 is to cover the establishment of procedures to inspect fire resistive joint systems. Both E 2174 and E 2393 include methods for field verification and inspection. Both standards are under the jurisdiction of Subcommittee E06.21 on Serviceability.

“Practices E 2174 and E 2393 provide standard, uniform inspection protocols that add value to the inspection process through consistency from project to project,” says Don Sabrsula, president, FireSafe of Houston, Inc., and a board member of the Firestop Contractors International Association (FCIA).

According to Sabrsula, E 2174 and E 2393 are essential parts of a “circle of quality” that include FM 4991, Standard for the Approval of Firestopping Contractors, an installation quality protocol developed by FCIA in conjunction with FM Approvals that is needed for a zero tolerance application.

Interested parties are invited to participate in ongoing revisions of both E 2174 and E 2393. For more information go to www.astm.org .





Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
How to use IPD; 2017 Commissioning Giants; CFDs and harmonic mitigation; Eight steps to determine plumbing system requirements
2017 MEP Giants; Mergers and acquisitions report; ASHRAE 62.1; LEED v4 updates and tips; Understanding overcurrent protection
Integrating electrical and HVAC for energy efficiency; Mixed-use buildings; ASHRAE 90.4; Wireless fire alarms assessment and challenges
Power system design for high-performance buildings; mitigating arc flash hazards
Transformers; Electrical system design; Selecting and sizing transformers; Grounded and ungrounded system design, Paralleling generator systems
Commissioning electrical systems; Designing emergency and standby generator systems; VFDs in high-performance buildings
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Fire & Life Safety Engineer; Technip USA Inc.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me