Project in Progress: Apex Friendship Middle School November 2017 update

Dewberry is making a lot of progress. Mechanical, electrical, and plumbing work is now being done onsite.

By Dewberry March 23, 2018
General work:
  • Classroom in Area B has the third-floor slab poured and roof is soon to be poured.
  • Remainder of building is dried in.
  • Windows and frames are currently being installed.
  • Site installation is in progress.
  • Drywall installation is in progress.
  • Ceiling installation is in progress.
  • Painting has started in some areas of the building.
Mechanical, electrical, and plumbing:
  • Plumbing domestic water and sanitary waste/vent piping installation is in progress throughout.
  • Electrical conduit and feeder installation is in progress throughout.
  • Mechanical ductwork and hydronic piping installation is in progress throughout.
  • Mechanical, electrical, and plumbing equipment has been installed throughout most of the building.
  • Fire sprinkler piping and equipment installation is in progress throughout.