Carl R. Darnall Army Medical Center October update
Mechanical and plumbing systems are nearly completed on all buildings. Finishes are underway in all areas.
October 2014 update:
- We have begun startup and checkout of equipment in all areas of the project.
- Rough in of mechanical and plumbing systems is nearly complete on all buildings; finishes are underway in all areas.
- Kitchen equipment is being installed.
- The chilled and steam plants are online and being commissioned.
- Final tab is underway in the West Clinic.
- Domestic hot water systems are online.
- Plumbing smoke and chlorination testing have begun.