Carl R. Darnall Army Medical Center May update
Hospital level 2 is partially ready for furniture move-in. Hospital level 3 punch is underway.
May 2015 update:
- Hospital level 2 is partially turned over for owner furniture move-in.
- Continuing hospital test-adjust-balance (TAB) for the bed tower (HL4-7).
- Hospital level 3 punch is underway.
- Continuing BSL3 point-to-point verification.
- TAB of operating rooms is underway.
- Interstitial Building System (IBS) floor punch is underway.