Your questions answered: Understanding Generator Set Rating Definitions

Nicholas Paolo, PE, regional sales engineer at MTU Onsite Energy tackled unanswered questions from the March 2, 2017, webcast on understanding generator set rating definitions.

03/07/2017


Nicholas Paolo, PE, regional sales engineer at MTU Onsite Energy tackled unanswered questions from the March 2, 2017 webcast on understanding generator set rating definitions.Various factors influence a generator set’s ratings, and how familiarity with these factors can contribute to more economical and reliable facility designs. The focus of this webcast includes ISO standards for generator sets rated for use in standby, prime, and continuous power applications, as well as flexibilities that generator set manufacturers use when rating their products—such as net power output versus gross power output—and their implications in terms of generator performance. In addition, various starting methods are compared including across-the-line start and soft-start solutions. EPA exhaust emission requirements are examined, as well as their implications in emergency, non-emergency, and mobile applications. Specific industry ratings, such as data centers, are reviewed and considered, including the implications when specifying generator sets.

Nicholas Paolo, PE, regional sales engineer at MTU Onsite Energy tackled unanswered questions from the March 2, 2017, webcast on understanding generator set rating definitions.

Question: What is the typical time that manufacturers use in their software between steps? We can design steps of delay via time clocks, time delay relays, or software. But how do we know that our time settings between steps match the generator vendor’s software time delay between steps?

Nicholas Paolo: The software assumes full recovery between steps. The report will state the time in seconds to recover from a step, which would represent the minimum delay time.

Q: Are you aware that some VFD manufacturers l recommend that the nonlinear loads should not be more than 20% of the generator capacity to minimize distortion of the generator output voltage waveform? Thus, the genset would have to be oversized, reducing the cost savings noted on your soft-start example. 

Paulo: Yes, MTU OE software has the ability to account for harmonics and oversize the generator. Other manufacturer sizing programs have similar functionality.

Q: What are the pros and cons of using an off-skid cooling system?

Paulo: The pros would be to locate the cooling package separate from the generator set, such as on the roof to be able to discharge heat if the cooling package cannot be located in front of the generator set. The cons could include added complexity, such as additional piping, pumps, valves, and power distribution for the motor on the cooling package.

Q: What is wet stacking?

Paulo: Wet stacking is a condition where hydrocarbons from the diesel fuel are not completely combusted and instead build up in the exhaust. Diesel engine generator sets are recommended to be operated at or above 30% of the generator set nameplate rating.

Q: Do you recommend fractional pitch 2/3, 5/6, etc. for onsite generators?

Paulo: The industry has standardized on 2/3 pitch today for backup generator sets, but custom generator pitch machines are available for applications, if required.



mark , NY, United States, 03/08/17 10:25 AM:

how do i get a certificate for continuing education?
HOWARD , FL, United States, 03/08/17 11:01 PM:

Wet stacking soot build up appears too be much BIO cooking Oils in the #2 high flash point exhaust system
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Integrating electrical and HVAC for energy efficiency; Mixed-use buildings; ASHRAE 90.4; Wireless fire alarms assessment and challenges
integrated building networks, NFPA 99, recover waste heat, chilled water systems, Internet of Things, BAS controls
40 Under 40; Performance-based design; Clean agent fire suppression; NFPA 92; Future of commissioning; Successful project management principles
Transformers; Electrical system design; Selecting and sizing transformers; Grounded and ungrounded system design, Paralleling generator systems
Commissioning electrical systems; Designing emergency and standby generator systems; VFDs in high-performance buildings
Tying a microgrid to the smart grid; Paralleling generator systems; Previewing NEC 2017 changes
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Fire & Life Safety Engineer; Technip USA Inc.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me