WTC office towers could be put off for decades

New World Trade Center office towers might not be built and occupied for nearly 30 years.

04/17/2009


According to an Associated Press report , construction of several ground zero office towers could be put off for decades because of the failing real estate market, the site's owners said Thursday, citing an analysis that projected one skyscraper might not be built and occupied until 35 years after Sept. 11, 2001.

Developer Larry Silverstein and the Port Authority of New York and New Jersey have been talking on and off for months about rewriting a 3-year-old agreement that gives the developer rights to build three out of five towers planned at the Sept. 11 terror attack site.

Silverstein, unable to obtain financing for all the towers and with only about $1 billion left in insurance money to pay for them, asked the Port Authority last fall to guarantee financing for two of his towers, officials familiar with the negotiations say.

The Port Authority agreed to back one tower already under construction, where the government agency has agreed to move once it's built. Executive Director Chris Ward on Thursday cited the exodus of major financial firms like Merrill Lynch and AIG from downtown Manhattan as a reason to not flood the market with 10 million square feet of office space at the same time - about 2013.
Ward also said that Silverstein was free to build his three towers on his own.





No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Combined heat and power; Assessing replacement of electrical systems; Energy codes and lighting; Salary Survey; Fan efficiency
Commissioning lighting control systems; 2016 Commissioning Giants; Design high-efficiency hot water systems for hospitals; Evaluating condensation and condensate
Solving HVAC challenges; Thermal comfort criteria; Liquid-immersion cooling; Specifying VRF systems; 2016 Product of the Year winners
Driving motor efficiency; Preventing Arc Flash in mission critical facilities; Integrating alternative power and existing electrical systems
Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
Designing generator systems; Using online commissioning tools; Selective coordination best practices
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
click me