When LEED isn't achieved, who's to blame?

For buildings that are projected to earn LEED certification but do not end up with enough credits, engineers could be held financially accountable.

07/13/2009


When building owners anticipate tax relief and promise certain sustainable features to tenants, not earning the projected U.S. Green Building Council LEED rating becomes a financial and legal problem, according to a Nashville Post article . The liability involved in beached LEED ambitions is new legal ground, largely because there's yet to be a court judgment on the books to set a precedent. But just because the courts have yet to see such a case doesn't mean the issue isn't brewing.

Design professionals, contractors, and building owners are the most likely targets for breach of contract lawsuits or negligence claims in these situations, according to Jeffrey King, an attorney and LEED AP. For example, if an engineer designs an HVAC system and it's installed properly, yet the system fails to achieve the desired reductions, fault is likely with the design team. However, if on paper the design is flawless, but a problem occurs in the installation, contractors will be targeted.
"Potential suits against design professionals are likely breach of contract or malpractice cases, professional liability cases," King said. "There [are lots] of questions as to whether the existing professional practice liability policies of some of these professionals cover these particular risks."





No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Combined heat and power; Assessing replacement of electrical systems; Energy codes and lighting; Salary Survey; Fan efficiency
Commissioning lighting control systems; 2016 Commissioning Giants; Design high-efficiency hot water systems for hospitals; Evaluating condensation and condensate
Solving HVAC challenges; Thermal comfort criteria; Liquid-immersion cooling; Specifying VRF systems; 2016 Product of the Year winners
Driving motor efficiency; Preventing Arc Flash in mission critical facilities; Integrating alternative power and existing electrical systems
Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
Designing generator systems; Using online commissioning tools; Selective coordination best practices
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
click me