University of Texas Tower Air Handling Unit Replacement

System overhaul: University of Texas Tower Air Handling Unit Replacement; EEA Consulting Engineers

08/09/2012


The University of Texas at Austin main building (the U.T. Tower) is shown during installation of the new air-handling unit. Courtesy: Flintco, the general contractor on the project. (Click to enlarge)Project name: University of Texas Tower Air Handling Unit Replacement

Location: Austin, Texas

Firm name: EEA Consulting Engineers

Project type, building type: System overhaul, school (college, university)

Project duration: 1.5 years

Project completion date: April 30, 2007

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $77,000

Engineering challenges

Location and space constraints for the new equipment: The tower was occupied and existing equipment remained in use for duration of the project. There was limited access to the area where existing and new equipment were located. This area is near the top of the tower, behind the walls that support the clock facings.

Time constraint for the switch over to the new system: The two-week Christmas break between the fall and spring semesters provided the only period that the tower was not occupied. The transition from the old air handling unit to the new one was scheduled for that period, which meant that all aspects of the project absolutely had to be completed and become fully operational during the break.

Solutions

Location and space constraints for the new equipment: The solution was to remove a portion of the wall below the north clock facing to allow access. A new equipment platform and stair system was constructed to support and access the new equipment in the tall void space inside the top of the tower. A crane was used to lift the equipment and material into place as well as to remove and replace the 2,700-lb wall stones.

Time constraint for the switch over to the new system: This entailed close coordination between EEA, the owner, the subconsultants, and the contractor. All parties committed early in the project to meet deadlines and to quickly address any issues that might arise. As a result, the switch over proceeded smoothly and the tower reopened as scheduled. Following the switch, final installation was completed.



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
High-performance buildings; Building envelope and integration; Electrical, HVAC system integration; Smoke control systems; Using BAS for M&V
Pressure piping systems: Designing with ASME; Lab ventilation; Lighting controls; Reduce energy use with VFDs
Smoke control: Designing for proper ventilation; Smart Grid Standard 201P; Commissioning HVAC systems; Boilers and boiler systems
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Consulting-Specifying Engineer case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
Integrating BAS, electrical systems; Electrical system flexibility; Hospital electrical distribution; Electrical system grounding
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.