Many people say, “Time is money.” However, material is too. When it comes to engineering, assembling, and testing control panels, reducing either time or materials (or both) can reduce costs significantly. Here are two examples that illustrate how reducing time and materials can also reduce costs. 

In the time reduction example, the estimated time to wire motor starters, contactors, and pilot devices is 4 hours and 29 minutes. However, the estimate is only 41 minutes if a device-level wiring system is used—an 85% reduction in wiring time. Engineering and testing times were also reduced.

Courtesy: Eaton

In the material reduction example, an installation that consisted of 1,600 motor starters would have required 7.83 miles of control wiring. However, by using a device-level wiring system, only 0.45 mile of flat cable was used. Calculating the material cost of each method using $0.61/ft for flat cable and $0.14 for #14 AWG, the device-level wiring system saved more than $4,300. In addition, the calculated savings for wiring/assembly time was 22 man-days.

Courtesy: Eaton

Another significant benefit is the device-level wiring network allowed the system to be installed and commissioned without having to ring out a multitude of control wiring connections. This type of control system can also connect electronic motor starters to the system, which allows motor current and other loads to be monitored without having to add current transformers or analog input cards to the PLC. This feature could enable a higher level of predictive data monitoring that was prohibitively expensive in the past.

This article appears in the Applied Automation supplement for Control Engineering and Plant Engineering



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Water use efficiency: Diminishing water quality, escalating costs; Lowering building energy use; Power for fire pumps
Building envelope and integration; Manufacturing industrial Q&A; NFPA 99; Testing fire systems
Labs and research facilities: Q&A with the experts; Water heating systems; Smart building integration; 40 Under 40 winners
Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.