Significant changes to the commercial provisions in 2012 IECC

10/15/2013


Air leakage

Figure 3: Fans set up in the doorway of a building to perform a full-building blower test, a compliance option listed in Section C402.4.1.2. Courtesy: Retrotec Inc.Except for climate zones 1 through 3, a continuous air barrier is required around the thermal building envelope (C402.4). Subsection C402.4.1.1 details the construction requirements of the air barrier and subsection C402.4.1.2 lists three compliance options, one of which is required to be met: materials, assemblies, or full building testing (see Figure 3). A table of maximum fenestration assembly leakage rates is provided in Section C402.4.3.

Unless required to comply with IBC Section 715 or 715.4 or UL 1784, doors and access openings from conditioned spaces into shafts, chutes, stairways, and elevator lobbies shall meet the fenestration requirements or be sealed per a newly added section (C402.4.4). Stairway, shaft, and outdoor air intakes and exhausts shall be provided with motorized dampers limited to a leakage rate of 4 cfm/sq ft. Gravity dampers meeting a 20 cfm/sq ft leakage rate are permitted as an exception for outdoor intakes and exhausts in climate zones 1 to 3, buildings less than 3 stories, as exhaust and relief dampers, and where the design outdoor air intake or exhaust capacity is ≤ 300 cfm. Dampers smaller than 2 ft in either dimension are permitted a leakage rate of 40 cfm/sq ft (C402.4.5).

Building envelope

Figure 4: Low-sloped roofs (<1/6 grade) directly above conditioned spaces in climate zones 1 through 3 must comply with roof reflectance and emittance requirements listed in newly added Table C402.2.1.1. Courtesy: A S Klein Engineering

Exposed outdoor piping insulation must now be protected from degradation, and use of adhesive tapes is not permitted (C403.2.8.1). Some exceptions to piping insulation requirements (C403.2.8) were also modified. The temperature range in exception 3 was decreased from 55 to 105 F to 60 to 105 F. Exception 5 no longer applies to piping 4 ft or less in length but instead to strainers, control valves, and balancing valves on piping with a diameter of 1 in. or less. Exception 6 was added that applies to buried piping conveying fluids ≤ 60 F.

Table C403.2.8, Minimum Pipe Insulation Thickness, was expanded, and the insulation thicknesses for very hot fluids and steam were increased tremendously; however, a footnote was added allowing a thickness reduction for direct-buried heating and hot water system piping. An exception was added to Section C404.5, Pipe Insulation, for heat-traced piping systems, specifying that they must meet the insulation thickness requirements per the manufacturer’s installation instructions.

A minimum insulation of R-3.5 is now required for radiant panels, associated U-bends and headers, and the bottom surfaces of structures incorporating radiant heating (C402.2.8).



LAWRENCE , PA, United States, 10/25/13 05:01 PM:

The article should state that very few states and jurisdictions are adopting the 2012 I Codes, and when they do, they are being amended. The reasons for not adopting are the Codes are that they are too complicated, too expensive, and cannot be fully enforced. Indeed, some states and jurisdictions are looking to move to a six year or longer code adoption cycle for these and other reasons. This move concerns the code writing groups, whose income is heavily dependent on selling books.
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Water use efficiency: Diminishing water quality, escalating costs; Lowering building energy use; Power for fire pumps
Building envelope and integration; Manufacturing industrial Q&A; NFPA 99; Testing fire systems
Labs and research facilities: Q&A with the experts; Water heating systems; Smart building integration; 40 Under 40 winners
Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.