Raised-Floor Facilitates Retrofit

A recent retrofit of a warehouse in downtown Kansas City, Mo., turned an 80-year-old structure into high-tech office space for the information technology department of DST, a financial services company. Helping to ease the facility's transition was the use of an underfloor-delivery system for the building's heating, ventilation and air-conditioning (HVAC) requirements, as well as the data an...

07/01/2001


A recent retrofit of a warehouse in downtown Kansas City, Mo., turned an 80-year-old structure into high-tech office space for the information technology department of DST, a financial services company.

Helping to ease the facility's transition was the use of an underfloor-delivery system for the building's heating, ventilation and air-conditioning (HVAC) requirements, as well as the data and power-cabling systems.

Client needs

DST processes transactions for mutual fund companies, and requires a reliable data and power infrastructure. Weaving these new systems into a facility that was built in the 1920s proved to be a challenge, according to David Rezac, the project manager with CDFM2, a local architectural firm.

"In order to expose the structure of the building for increased aesthetic value, to provide the tenant with exceptional flexibility and provide a greater floor-to-floor height for better lighting solutions, we decided to propose a raised-floor HVAC system," explains Rezac.

The decision to utilize a raised-floor HVAC system facilitated a number of other benefits, including reduced construction costs, greater flexibility for the future, quality comfort control and even the design of a new middle floor.

System specifications

Four 40-ton rooftop units provide air to the pressurized plenum, and the entire HVAC system is variable-air-volume, which offers good comfort control and energy savings.

Because air moves in the plenum between the structural floor and the access floor, conventional ceiling ductwork could be eliminated, saving installation costs and freeing overhead space.

Also, the building space provides flexibility for the future because office rearrangement costs are very low. The floor-vent terminals could be installed anywhere in the raised-floor grid, because the entire area under the floor becomes a pressurized air plenum. To reconfigure workstations, maintenance personnel simply remove one or two access floor panels to relocate voice, data and power cabling. Then, they can move the air terminals, bringing conditioned air to the reconfigured space as needed.





No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Combined heat and power; Assessing replacement of electrical systems; Energy codes and lighting; Salary Survey; Fan efficiency
Commissioning lighting control systems; 2016 Commissioning Giants; Design high-efficiency hot water systems for hospitals; Evaluating condensation and condensate
Solving HVAC challenges; Thermal comfort criteria; Liquid-immersion cooling; Specifying VRF systems; 2016 Product of the Year winners
Driving motor efficiency; Preventing Arc Flash in mission critical facilities; Integrating alternative power and existing electrical systems
Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
Designing generator systems; Using online commissioning tools; Selective coordination best practices
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
click me