Project name: Learning Center Expansion

Project type: Addition to an existing building

Engineering Firm: exp

Building type: Office building; customer education center

Location: Verona, Wis.

Timeline: August 2010 – September 2011


Break room exterior. Courtesy: expBuilding details

This project was an addition to an existing customer training facility and employee office building.  The project included 2 floors of meeting rooms above a single floor of housing over 230 private offices.  Total project size was approximately 198,000 sq ft. Each private office received individual heating/cooling controls, occupancy sensors for lighting and variable air volume (VAV) operation reduction, and window monitors on all perimeter offices to disable mechanical supply to those rooms.  Fully integrated audio-visual (AV) controls were included in the training rooms to allow for interconnection of all lighting, projector operation, window shades and sky-fold room partitions.  Concourse lighting included fixtures designed by the lighting engineer to reflect and compliment concourse lighting in the existing portions of the building.

Project details

As the engineer of record on both this project, and the existing building, the engineering team was very familiar with the existing systems which allowed them to be instrumental in major revisions to the mechanical, electrical, and plumbing (MEP) systems. This included the following:

Electrical System: Two existing pad mounted transformers were in the way of the building expansion.  An existing 1250 kW building generator was also going to be encompassed in the center of the building with the new expansion.  Therefore, phased revision occurred by first locating a medium-voltage generator remotely on the site, and transferring down to 480 V within the building, allowing the generator to be removed while keeping the building fully backed up. The space made available from the removal of the generator allowed a dual transformer unit substation to be added as a replacement for the pad mounted transformers. This allowed the necessary space to be used for the building's construction. 

Meeting Level Concourse. Specialty fixtures were designed specifically for the expansion project. Courtesy: expMechanical: Four existing boilers providing hot water for perimeter radiation were removed and replaced as part of this project with high temperature multi-stack water-to-water heat pumps. Two 80,000 cfm Haakon custom rooftop units with economizers provide HVAC supply to the project. Three 200 hp geothermal pumps provided the means for connecting the building heating/cooling system to the vertical bore, closed loop, geothermal system. 

Plumbing: Relocated the domestic water supply due to the new building location with minimal downtime to keep building operational as close to 100% as possible.  Tied in emergency back up to the mechanical system in case of geothermal system failure. 

Fire Protection: Fully protected building. 

Lighting: High use of LED fixtures with a fully automated lighting control and dimming system.



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Water use efficiency: Diminishing water quality, escalating costs; Lowering building energy use; Power for fire pumps
Building envelope and integration; Manufacturing industrial Q&A; NFPA 99; Testing fire systems
Labs and research facilities: Q&A with the experts; Water heating systems; Smart building integration; 40 Under 40 winners
Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.