Project name: Henkels & McCoy Headquarters Emergency Generator

Project type: Addition to existing building

Engineering Firm: Henkels & McCoy

Building type: Office building

Location: Blue Bell, PA, United States

Timeline: November 2012 - October 2013


Previous 5kV Main Switchgear, manufactured in 1974. All images courtesy of Henkels & McCoy.

Project goals

  • Provide a reliable, low-cost backup generator solution to power the Jolly Road facility during loss-of-utility events.
  • Provide H&M with additional revenue from PJM “Demand Response Program”. This includes being able to take H&M off-grid while the utility is still operating, using closed-transition switching.

Building details

There are two buildings on this property. One building contains 6,000 sq ft of automotive maintenance area, 14,000 sq ft of warehouse storage, and another 9,000 SF of office space. The other building contains about 46,000 sq ft of office space, plus a cafeteria and a large data center and copy center.

Project details

Engineering, Construction, and the Henkels & McCoy Maintenance Department designed and installed a 4kV, 750kW generator. Engineering and all concerned Newly completed substation yard and generator.worked with vendors to provide the most cost effective approach to this purchase and implementation. The generator was fed directly into a G&W Automatic Transfer Control Switchgear, which replaced the existing 35 year old switch. Requirements for participation in Demand Response Programs were evaluated; it was determined to be less important than providing effective, economic backup power.

Project success

The project's success was clearly demonstrated during the recent power outages in the area from an ice storm. When the area lost power, the entire Henkels & McCoy facility was able to stay powered up and respond with line crews and other personnel and equipment. In addition, the other employees could perform their work, reducing the amount of downtime and expenses related to sending employees home.


Henkels & McCoy, 985 Jolly Road, Blue Bell, PA 19422



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Combined heat and power; Assessing replacement of electrical systems; Energy codes and lighting; Salary Survey; Fan efficiency
Commissioning lighting control systems; 2016 Commissioning Giants; Design high-efficiency hot water systems for hospitals; Evaluating condensation and condensate
Solving HVAC challenges; Thermal comfort criteria; Liquid-immersion cooling; Specifying VRF systems; 2016 Product of the Year winners
Driving motor efficiency; Preventing Arc Flash in mission critical facilities; Integrating alternative power and existing electrical systems
Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
Designing generator systems; Using online commissioning tools; Selective coordination best practices
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
click me