Power management system enhances emergency response

Case study: A super-tall building in the Middle East.

03/20/2014


A super-tall building in the Middle East contains three levels of enclosed underground parking, a hotel with multiple ballrooms and restaurants, several floors of offices, and multiple residential and observatory levels. Seven floors will host the building’s mechanical, electrical, plumbing (MEP), and fire protection equipment, which will use district-chilled water as a cooling source and feature three main chilled water pressure zones.

The building’s generator power systems will serve the following loads: fire pumps, fire transfer pumps, firefighter elevators, emergency evacuation elevators, emergency lighting system, safety and alarm systems, stair pressurization systems, lobby pressurization systems, public corridor exhaust systems, refuge floor pressurization systems, garage exhaust fans, partial building cooling load and associated equipment, and partial refuge floor cooling.

Three base building generators are located in each plant to support the life safety systems. Two plants are interconnected, providing reliable redundancy and backup for the building’s emergency power distribution system.

Like other super-tall buildings, there is a discrepancy between the code-required peak design demand and the building’s actual peak power usage. To take advantage of the additional power capacity already designed into the facility, the building’s power management system is programmed to accommodate a second and third tier of MEP systems that will enhance building response in the event of an emergency. This includes the building’s garage exhaust and corridor exhaust systems, life safety equipment supporting cooling devices, and refuge floor cooling.

During a power outage and after life safety Category 1 and legally required Category 2 systems were activated, then the third category is potentially energized. The power blocks in the third tier will be assessed based on each individual block’s power requirements and power availability. For example, the underground garage system was designed with 14 individual zones and allocated to the third tier. Upon receiving a signal simultaneously, all exhaust fans within this zone and adjacent zones will be activated. After necessary garage exhaust systems are online, the next power block in the third tier could also be activated if there is ample power capacity.

 

 


Suzan X. Sun-Yuan is a senior associate and lead mechanical engineer with Environmental Systems Design. She has experience with super-tall buildings, food labs, and central plant designs and upgrades. Mohsen Aghai is a senior associate and lead electrical engineer with Environmental Systems Design. He has experience with super-tall, mixed-used, commercial, and governmental buildings as well as hospitals and central plant designs and upgrades.

 



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Water use efficiency: Diminishing water quality, escalating costs; Lowering building energy use; Power for fire pumps
Building envelope and integration; Manufacturing industrial Q&A; NFPA 99; Testing fire systems
Labs and research facilities: Q&A with the experts; Water heating systems; Smart building integration; 40 Under 40 winners
Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.