Texas Medical Center in Houston, Texas, faced its own emergency medical requirements in June 2001, after Tropical Storm Allison dumped 39 inches of rain in the area in just two days. The center, which covers more than 700 acres and incorporates more than 100 permanent buildings, including 13 hospitals, two specialty institutions, two medical schools and two nursing schools, faced severe floodin...

12/01/2002


Texas Medical Center in Houston, Texas, faced its own emergency medical requirements in June 2001, after Tropical Storm Allison dumped 39 inches of rain in the area in just two days. The center, which covers more than 700 acres and incorporates more than 100 permanent buildings, including 13 hospitals, two specialty institutions, two medical schools and two nursing schools, faced severe flooding damage. Basements housing power supplies filled with water, knocking out transformers, switches and other electrical equipment.

"It was unbelievable," said Danny Colwell, president of the center's electrical-contracting firm, Colwell Electric. "Switches, generators, transfer switches-all underwater."

Quick responsiveness of the center's switchgear supplier helped speed the center's recovery. Colwell was able to order $100,000 of replacement parts immediately, an order that required coordination among several of the manufacturers' service centers. The initial order, including 40 new transfer switches, was placed on a Friday. New switches began arriving the next Wednesday, despite a typical turnaround time of six to 10 weeks. They continued to arrive at a rate of three or four switches a day. To help expedite the process, the manufacturer's Dallas office sent six sales people to Houston to handle paperwork and keep order processing and shipping moving forward.

Critical areas at the medical center were up and running within six days. Service to remaining areas was restored in less than a month.

From Pure Power, Winter 2002





No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Combined heat and power; Assessing replacement of electrical systems; Energy codes and lighting; Salary Survey; Fan efficiency
Commissioning lighting control systems; 2016 Commissioning Giants; Design high-efficiency hot water systems for hospitals; Evaluating condensation and condensate
Solving HVAC challenges; Thermal comfort criteria; Liquid-immersion cooling; Specifying VRF systems; 2016 Product of the Year winners
Driving motor efficiency; Preventing Arc Flash in mission critical facilities; Integrating alternative power and existing electrical systems
Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
Designing generator systems; Using online commissioning tools; Selective coordination best practices
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
click me