Due to the high energy use at this all-electric police building, exp U.S. Services was brought in to perform retro-commissioning and assess the problems and potential for energy savings. This large, 12-year-old, 5-story building houses the administrative offices for the police department, which was supposedly occupied 24/7. In reality, only a small portion of the building is occupied continuously. Two large air handling units (AHUs) serve the entire building through variable air volume (VAV) and fan-powered boxes (FPBs).

During the inspection, 20 of the 100 perimeter FPBs were found inoperative. These boxes are the only source of heat, and tenant comfort issues were common. Further investigation revealed some incorrect coding in the building automation system (BAS) programming was permanently holding these boxes in “unoccupied” mode. This error was corrected quickly, and all boxes began functioning properly. Although this was not directly an energy conservation item, it allowed the building operators to shut off the AHUs during winter nights because the FPBs would operate independently, and provide heat as needed. It appears that the BAS programming for these particular boxes was overlooked during the initial start-up of the HVAC systems.

The lighting in the building is adequate, and reasonably efficient fixtures were used, but at some point during design, the wall-mounted light switches were “value-engineered” out of the building. The theory was because the building would be occupied 24/7, the lights would never be off, and the switches were superfluous. In reality, only a small portion of the building is occupied continuously and the lights are left on 24/7, wasting large amounts of energy. Area-wide lighting controllers were installed, but subsequently taken out of service due to complaints of lights going off at the wrong times or other problems.

It seems that the proper design review by the CxA would have addressed this issue, and perhaps suggested an alternative design, such as occupancy sensor light switches that would control the local lighting and avoid the current energy waste. exp’s recommendation was to install an occupancy-sensing switch for each lighting circuit in the building. Although a costly option, the annual savings are 1,440,000 kWh and $102,000 for a payback of less than 1 year. 


Terrence Malloy is project manager for the energy solutions group at exp US Services Inc. He focuses on energy conservation, retro-commissioning, and renewable energy systems.



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Water use efficiency: Diminishing water quality, escalating costs; Lowering building energy use; Power for fire pumps
Building envelope and integration; Manufacturing industrial Q&A; NFPA 99; Testing fire systems
Labs and research facilities: Q&A with the experts; Water heating systems; Smart building integration; 40 Under 40 winners
Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.