How to engineer systems in mixed-use buildings: Electrical and power systems

When working on mixed-use buildings, engineers must address many needs in one building. Electrical and power engineering are key aspects of these buildings.

09/30/2012


Mark Crawford, Principal engineer, Southland Industries, Las VegasChristopher M. Kearney, PE, LEED AP, Project manager, exp, Maitland, Fla.Brian McLaughlin, Associate, Los Angeles, Arup

Participants:

Mark Crawford, Principal engineer, Southland Industries, Las Vegas

Christopher M. Kearney, PE, LEED AP, Project manager, exp, Maitland, Fla. 

Brian McLaughlin, Associate, Los Angeles, Arup


 CSE: What’s the one factor most commonly overlooked in electrical systems in mixed-use buildings? 

Kearney: It is hard to narrow this down to one factor, but the first two that come to mind are metering and voltage requirements, since you may have 120/240 V single-phase for residential units and 277/480 V 3-phase for commercial areas. This will require input and coordination from the owner and utility company. 

CSE: Describe a recent project in which you had complex metering and submetering in a mixed-use building. 

Kearney: We are currently working on a six-story building that included two commercial retail tenants, apartments, and a multi-level parking garage with a fire pump. Separate metering was required for the fire pump, apartments, and retail tenants, which includes back-of-house power for lighting, mechanical equipment, etc. 

CSE: How do you balance the need for reliable power with the desire for efficiency and sustainability?

Kearney: When we incorporate renewable power sources (i.e., wind, solar, bio-gasification, etc.) into the building designs, we suggest the building should remain connected to the grid as the grid is your “battery.” With this design, there is no question about these systems’ reliability as they are there for their sustainability benefits. If the question is about having to have reliable power for a project (e.g., data centers), then it is just part of the project and sustainability is a completely independent issue. Efficiency and sustainability are becoming more and more important in all of the building types we work on. We must design more efficient buildings. This can be done by appropriately selecting system types and purchasing more efficient equipment in those systems. We must spend more money here. Renewables are an extension (not a substitution) of this foundation when we are reaching to become closer to carbon neutral projects.



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Integrating lighting, HVAC systems, Energy codes and lighting, BIM and fire protection engineering
Engineering hospital electrical systems, Boilers and boiler systems, Building envelope best practices
Hospital indoor air quality, ASHRAE 90.1 update, Specifying piping materials, Integrated project delivery
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Consulting-Specifying Engineer case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Estimating data center PUE, Design tips for cost savings, Networked controls, NFPA 70E
Preventing arc flash, Backup power fuel choices, power for high-tech facilities
Using BIM in electrical power design; Closed-transition transfer; Medium-voltage distribution; Diesel emission regulations; Increasing emergency power capacity

Poll of the Week

When engineering systems in military buildings, what’s the most difficult issue you face?
Automation and controls
Codes and standards
Electrical and power
Energy efficiency, sustainability
Fire and life safety
HVAC


Click Here for Poll Archives
Sponsored by:

About Us | Contact Us | Advertise | Subscribe to Magazine | Site Map | Privacy Policy
Home | Channels | New Products | Media Library | Connect | Industry News | Events and Awards | Newsletters | Blogs | Magazine
Control Engineering | Plant Engineering | Consulting-Specifying Engineer
All content copyright © 2010-2013 CFE Media. All rights reserved.